24647 Seaview Tce Enviro Mgmt Plan

Attached to the e-mail MCU14/0084 Environmental Management Plan (71 Seaview Tce).

of 212

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (18.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
List of Referenced Legislation & Codes of Practice – Environment
HB-HSEQ-F-005-A Version 5
           Issues            Applicable Legislation / Guidelines / Standards    Regulating                      Major Requirements Of Legislation
                                                                                 Authority

 Erosion and sediment       Protection of the Environment Operations Act 1997   NSW EPA         Must not deposit sand, soil, silt or mud—
 control                                                                                         - in a roadside gutter, stormwater drain or a water; or
                            Best Practice Erosion & Sediment Control 2008Best                    - in a place where it could move or be washed into a roadside gutter, or
                            Practice Erosion & Sediment Control 2008                             stormwater drain
                                                                                                Local council can develop environmental plans to manage erosion and
                                                                                                 sediment erosion issues. Check with the appropriate local council for
                                                                                                 further details
                                                                                                Minimisation of erosion and control of sediment in all construction
                                                                                                 activities.
                                                                                                Use of erosion control matting to minimise soil erosion on steep slopes
                                                                                                 and for highly erosive soils.
                                                                                                Stabilised entry and exit points to minimise tracking of sediment offsite.
                                                                                                Sediment control for service trenches.
                                                                                                Preserve as much soil cover (grass, leaf litter, gravel and erosion control
                                                                                                 mats) as possible.
                                                                                                Maintain kerb vegetation where practicable to filter out sediment
                                                                                                Commence earthworks immediately prior to building.
                                                                                                Topsoil should be stockpiled (with cover) for later use.
                                                                                                Building materials should be located within the sediment control zone.
                                                                                                A perimeter bank may be required upslope of a stockpile.
 Waste Management
 Disposal of waste from     Protection of the Environment Operations (Waste)    NSW EPA         Outlines the requirements of a waste management program such as the
 building sites             Regulations 2005                                                     activities that may generate waste

 Management of              Protection of the Environment Operations (Waste)    NSW EPA         Minimisation of waste generated
 Excavated Material         Regulations 2005                                                    Ensure the correct storage of waste and segregation of different waste
                                                                                                 materials.
                                                                                                A waste management program may be required as part of the
                                                                                                 development approval conditions.
                                                                                                Protect the environment through the minimising the amount of
                                                                                                 excavation required.
                                                                                                Use excavated material as backfill.
                                                                                                Where large excavation is required, stockpile topsoil and replace on
                                                                                                 completion of works.
                                                                                                A specific site rehabilitation program may need to be followed




HUTCHINSON BUILDERS                                                                                                                                                       17
Log in to download the original file

24647 Seaview Tce Enviro Mgmt Plan.pdf · 18.0 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.