24647 Seaview Tce Enviro Mgmt Plan

Attached to the e-mail MCU14/0084 Environmental Management Plan (71 Seaview Tce).

of 212

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (18.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                                                                                                              MCU14/0084

                          b.      indicate provision for on-site and off-site parking and shuttle buses (if required) for
                                  the required workforce
                          c.      indicate the location of loading and unloading areas within the site
                          d.      indicate the location of any “holding” areas for heavy vehicles
                          e.      operating hours.
                  19.     Construction staff must not park within Seaview Terrace, the Council carpark in Seaview
                          Terrace, McAnally Drive or any other surrounding street. Parking must either be on site
                          or at a suitable off-site location serviced via a shuttle bus. Details must be included in
                          the Traffic Management Plans for the site.
                          Earthworks
                  20.     Earthworks required on site must be carried out in accordance with Council’s Planning
                          Scheme Policy PSP5 – Engineering Design Standards so as not to cause the additional
                          ponding of water on any adjoining lands or the blockage of, or interference with, any
                          natural watercourses.
                  21.     The use of vibratory equipment of any kind is not permitted to be used (including
                          vibrating rollers and the use of vibrating installation techniques for sheet piling and other
                          construction vibrations caused by excavating, earthmoving or demolition machinery or
                          other similar construction techniques) unless approved and supervised by a Certified
                          Geotechnical Engineer. Under such circumstances the operator of such equipment must
                          at all times comply with the directions of the Geotechnical Engineer.
                  22.     The excavation of the site and the construction of the proposed works must not have any
                          adverse effects on the stability of adjoining buildings and/or structures and/or services
                          and/or lands. In this respect, a Registered Professional Engineer Queensland must
                          supervise the excavation of the site and the construction of the new works to determine
                          whether any additional measures are required to protect the stability of adjoining
                          buildings and/or structures and/or services and/or lands.
                          Site Stability
                  23.     The design and construction of the development must be carried out generally in
                          accordance with the Geotechnical Study prepared by Morrison Geotechnic Job:
                          DE14/231 dated October 2014 and the “Structural Design Concept” Job No14517 Issue
                          B prepared by TOD Noosa dated 29 July 2014. The documents must be revised to
                          include the following:
                          a.      a contingency plan and alternative design should the piled footing system as
                                  designed not be achievable due to unsafe working conditions or unexpected
                                  ground conditions
                          b.      the document must be submitted to Council at the time of Operational Works
                                  approval.
                  24.     Should the recommendations of the geotechnical report or contingency plan require any
                          part of the works (including excavation, retaining structures, tie backs, etc.) to be
                          temporarily or permanently constructed within any adjoining property, a letter of authority
                          from the adjoining property owner(s) must be obtained prior to the issue of the building
                          permit.
                  25.     A suitably qualified and accredited consultant must undertake a detailed check to
                          establish that a stable working platform has been constructed in accordance with the
                          design prior to the use of heavy equipment or plant likely to cause vibrations on the site.
                          Certification of the works to this stage must be provided to Council.
                  26.     A suitably qualified and accredited consultant must undertake a detailed check to
                          establish that the screw pile and CFA piles have been installed in accordance with the
                          design and that the required pile capacities have been achieved. Certification of the pile
                          systems must be provided to Council.
                                                                                                            Page 4 of 11

Document Set ID: 19879056
Version: 1, Version Date: 16/03/2015                                                                     Print Date: 16 March 2015, 2:32 PM
Log in to download the original file

24647 Seaview Tce Enviro Mgmt Plan.pdf · 18.0 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.