24647 Seaview Tce Enviro Mgmt Plan

Attached to the e-mail MCU14/0084 Environmental Management Plan (71 Seaview Tce).

of 212

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (18.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Environmental Management Plan
24647 – 71 SEAVIEW TCE SUNSHINE BEACH

The objectives will be achieved through the management commitment, strategies and monitoring programs outlined in this EMP and
related plans.


2.2              Project Scope and Description
The project comprises the construction insert job specific details here:

          Architecturally designed house built into the side of a hill
          Three-level high-end residence
          Circular lift
          Resort style pool and grounds
The project is expected to be completed within 24 months with a commencement in July 2016 and completion in July 2018.
Activities undertaken on the construction site and the timeframe in which these activities occur during the time which the site is
operational are outlined in Table 1. The Site Layout with erosion and sediment control measures is provided in Appendix G.

TABLE 1

Construction time frames

    Activity                                                         Estimated Timeframe
    Site Establishment                                               1 week
    Demolition                                                       N/A
    Foundation and bulk earth work                                   4 months
    Structure                                                        12 months
    Fit out and Finishes                                             12 months
    External works                                                   3 months


2.3              Structure of the Environmental Management Plan
The EMP consists of:

     This overarching Environmental Management Plan which describes the environmental management system for the works in
      alignment with ISO 14001.

     Element based Environmental Work Method Statements (EWMS) which details the specific objectives / performance standards,
      control measures, monitoring and responsibility for the various environmental aspects associated with the works.
     Element based sub-plans for environmental aspects which carry a higher environmental risk.
The following supplementary documentation below in Table 2 may be required to be incorporated with the EMP. these documents
may be provided by an external agent.

TABLE 2

Supplementary Documentation

    Reference Element                                                Elements(s)

    EWMS-1                                                           Erosion and Sediment Control (Stormwater Management)

    EWMS-2                                                           Waste Management
    EWMS-3                                                           Pest Control and Fauna Management
    EWMS-4                                                           Vegetation and Weed Management
    EWMS-5 – N/A                                                     Acid Sulfate Soil Management
    EWMS-6 – N/A                                                     Fire Ant Management




HUTCHINSON BUILDERS                                                                                                            8
Log in to download the original file

24647 Seaview Tce Enviro Mgmt Plan.pdf · 18.0 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.