Appendix B - Global Stability Assessment Report
Attached to the e-mail Operational Works Application - DA Form 1 - Town Planning Report - Global Stability Assessment Report - Earthworks Compaction Report - Erosion and Sediment Control Plan - 36 Tunba Court Cooroy Mountain.
The original of this document is very large (10.3 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
- 13 -
Job No: ME21/032
Suitable vegetation, plants must be maintained over the batter surfaces. Hydro-mulch or similar
may be considered in steep areas. A qualified and competent landscape consultant or
agronomist should be contacted for further information as required.
All permanent fill batters and any permanent cut batters (not anticipated) must be covered
with suitable vegetation as soon as possible after construction to reduce the potential for
surface scouring, erosion and any possible dispersion.
In areas where the geometry differs from that shown in the models (if encountered), further
assessment may be required. This office should be contacted if in any doubt.
Additional cut or fill earthworks, beyond those shown in the provided section and described in
this report, should not be carried out adjacent to the batter or retaining wall locations assessed
as additional earthworks will affect the global stability of the batters and retaining walls.
The batters and retaining walls must not be undermined. Excavations shall not be carried out
adjacent to the batter or retaining wall toes.
Irrigation of all slopes, other than to establish vegetation, must be restricted as excessive
watering on and behind the slopes can cause saturation, which can result in ground
instability.
If onsite effluent disposal systems are to be used further advice must be sought from a
consultant suitably qualified and competent in this area. Onsite effluent disposal may cause
dispersion and erosion of the soils and more weathered rock at the Site.
Any underground services connections should be flexible.
Underground services must be regularly assessed for leaks and repaired where necessary.
The proposed shed should be founded in a consistent subsurface profile (e.g residual hard
clays or weathered granite/granodiorite rock). Otherwise, suitable articulation should be
designed and constructed between portions of the shed founded in different subsurface profiles
(e.g combination of controlled fill and natural soils or weathered granite/granodiorite rock).
10.0 LIMITS OF GLOBAL STABILITY ASSESSMENT
This Report has been prepared by Morrison Geotechnic Pty Ltd (Morrison Geotechnic), and may
include contributions from Morrison Geotechnic’s officers and employees, sub-contractors, sub-
consultants or agents (Contributors).
This Report is for the sole benefit and use of Mr Geoff Hussin (Client) and approved parties for the sole
purpose of providing geotechnical advice and recommendations in respect of the existing cut and fill
batters at 36 Tunba Court, Cooroy Mountain (Project). The Report is only intended to address those
issues expressly described in the scope of work in this Report.
This Report should not be used or relied upon for any other purpose without Morrison Geotechnic’s
prior written consent. Morrison Geotechnic and the Contributors do not accept any responsibility or
liability in any way whatsoever for the use or reliance of this Report by anyone other than the Client or
by anyone for any purpose other than that for which it has been prepared.
Except with Morrison Geotechnic’s prior written consent, this Report may not be:
(a) released to any other party, whether in whole or in part (other than to the Client’s officers,
employees and advisers);
(b) used or relied upon by any other party; or
(c) filed with any Governmental agency or other person or quoted or referred to in any public
document.
Morrison Geotechnic and the Contributors, do not accept any liability or responsibility whatsoever for,
or in respect of, any use or reliance upon this Report by any third party. Morrison Geotechnic is not
obliged to enter into discussions with any third party in respect of this Report.
The information (including technical information and information obtained through discussions) on
which this report is based has been provided by the Client and third parties. Morrison Geotechnic and
the Contributors:
(a) have relied upon and presumed the accuracy of this information;
Ref: 27222-rev 1 MORRISON GEOTECHNIC
Mr Geoff Hussin
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.