2015-03-09 General Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
GENERAL COMMITTEE MEETING AGENDA 9 MARCH 2015
At quotation close on 23 February 2015, submissions had been received from four respondents:
A. Carruthers Contracting
B. Aspect Contractors
C. Sayer Civil Pty Ltd
D. Shadforths Civil Engineering Contractors Pty Ltd
The evaluation panel noted that the submissions were of satisfactory standard. One quotation
was below the consulting engineer’s estimate. The other three were fairly close in price but well
above the consulting engineer’s estimate.
The evaluation panel considers the offer from Carruthers Contracting to be the most
advantageous to Council.
The preferred contractor has been interviewed and additional information sought and they appear
capable of completing the works in the nominated construction period of 12 weeks, weather
permitting. The timing should meet Council’s obligations of completing the project by 30 June
2015 in terms of a state government grant.
Previous Council Consideration
Nil.
Impact on Wallace Park Operations
The project is being planned so that:
1. Access to Wallace Park is available at all times off the Eumundi Noosa Road roundabout
(the safest access point).
2. The informal parking area on the Gibson Road extension is extended on a temporary basis
to cater for the disruption to existing parking (which is 100% utilised at times).
3. Only one of the car parks off Wallace Drive is to be closed at a time for construction of
concrete thresholds on the driveways.
At a recent meeting with seven of the community groups that use the Wallace Park area, there
was general support for the project but suggestions were made for ways to help minimise the
disruption (i.e. to ensure good temporary pathways are installed for the elderly, provide additional
disabled car spaces in the precinct car parks.). The suggestions made will be considered as part
of the construction work.
Finance & Risk
The project is 50/50 funded by Council and the Cycle Network Local Government Grants
program 2014/15.
Council Funds $200,000
Grants Funds $200,000
Total Budget $400,000
The project does not involve any undue risk, however a contingency allowance is proposed for
unforeseen issues plus managing car parking and pedestrians.
The grant application includes the installation of lighting. The cost of street light installation for the
raised threshold pedestrian crossing on Wallace Drive will be required at a cost of approximately
$43,000.
Page 4 of 70
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.