GENERAL COMMITTEE MEETING AGENDA 9 MARCH 2015
There will also be Council costs involved regarding internal project management, pruning of
trees, managing impacts on Wallace Park, etc.
Project costs
Total budget $400,000
Design costs $15,000
Available Budget $385,000
Contract price $318,040
Contingencies $19,960
Consultant design finalisation $3,000
Street lighting $43,000
Consultant supervision $15,000
Council costs $13,000
Total $412,000
Potential shortfall $27,000
If the additional funds are required a budget adjustment will be sought as part of Budget Review
4.
Consultation
External Consultation - Community & Stakeholder
The project manager has consulted with community groups at Wallace Park.
Internal Consultation
Council’s Procurement and Contracts Officer and Workplace Health & Safety Officer have been
involved during the tender process.
Departments/Sections Consulted:
X Community Services X Planning & Infrastructure
Disaster Management & Public Order Building & Plumbing Services
Waste & Environmental Health DA Planning
X Community Facilities Strategic Land Use Planning
Cultural Facilities X Asset Design & Investigations
Asset Planning
Civil Operations
Environment
Executive Office X Corporate Services
Community Engagement Finance
Customer Service ICT
Executive Support X Procurement & Fleet
Governance Property & Facilities
Human Resources Revenue Services
Page 5 of 70
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.