Response to Stormwater Management Approval Conditions Letter
Attached to the e-mail Operational Works Application OPW16 /0203 - 1 of 4.
4 of 6
65. Stormwater Quality Treatment must be designed in accordance with the Water by Design MUSIC modelling
Guidelines. Any deviation away from the recommendations of the Water by Design guidelines may only be
approved where:
65.1. Letters signed by the authors of the Water by Design MUSIC modelling guidelines and/or eWater
MUSIC modelling program are provided to confirm that the modelled design is expected to meet the
required water quality outcomes at the discharge point of the site; and
Response
As detailed in Section 4 of the SWMP Report No. 16-001014-01A, modelling of the site and design of stormwater
quality treatment devices have been undertaken in accordance with Water By Design MUSIC Modelling Guidelines
(2010) and other relevant Water By Design guidelines. The SWMP Report No. 16-001014-01A demonstrates that
WQOs for the site are achieved without modelling of the Water Quality Control Pond (WQCP). This is conservative
considering that the proposed pond will capture suspended solids through sedimentation and will treat some
nutrients. Furthermore, the proposed Gross Pollutant Traps (GPTs) were excluded from the modelling, which are
also expected to capture gross pollutants and suspended solids. The only treatment devices modelled are the
Bioretention Basins, which have been configured in accordance with Water By Design’s MUSIC Modelling
Guidelines (2010). Therefore, since there is no deviation from the recommendations specified in Water By Design
Guidelines, a letter from the authors of the Water By Design guidelines or eWater MUSIC program is not required.
For email correspondence with Water By Design and eWater regarding the modelling of the pond, refer to Calibre
Consulting Letter No. B14158.W-10A dated 5 February 2016.
65.2. A contingency plan to monitor for and to remove cyanobacterial and algal outbreaks from
waterbodies, including costs, is provided for approval with the Operational Works application and the
approved version is implemented throughout the lifetime of the development. All stormwater runoff
treatment must be undertaken within the development areas of the site. Stormwater likely to contain
grease and oil (i.e. from all roads and car parking areas) shall be managed via grease and oil
arrestors prior to treatment within bioretention basins, wetlands and water quality control ponds.
Response
As discussed above, modelling of the site and design of stormwater quality treatment devices have been undertaken
in accordance with Water By Design MUSIC Modelling Guidelines (2010) and other relevant Water By Design
guidelines. As detailed in Section 4 of the SWMP Report, all stormwater treatment is undertaken within development
areas of the site. Modelling has demonstrated WQO’s can be achieved prior to discharge from the site.
Stormwater from all significant roads and car parking areas are proposed to be treated with a HumeGard GPT.
Council specify that runoff from all road and car parking areas is to be pre-treated for grease and oil prior to
discharging to the downstream Bioretention systems. According to Water By Design Bioretention Technical Design
Guidelines (2014) Bioretention systems are suitable for treating runoff from roof, ground and road areas. Table 14 of
the guidelines outlines pre-treatment measures typically proposed upstream of Bioretention Basins based on
catchment size (i.e. for catchments between 2ha and 5ha vegetated swales, coarse sediment forebays, inlet pond or
GPT’s are recommended). The condition to pre-treat all runoff from road and car parking area specifically for oil and
grease prior to discharge into Bioretention Basins is considered to be conservative given the nature of the
Bioretention treatment device. There are also many examples of urban, commercial and industrial development that
propose Bioretention Basins without pre-treatment of oil and grease.
As per details provided in Section 3.1 of the Stormwater Management Construction & Maintenance Plan Report No.
16-001014-02A, the HumeGard GPT proposed upstream of the proposed Bioretention Basins has the capability of
trapping floating oil and grease pollutants. As demonstrated on Page 2 of the HumeGard GPT Technical Manual
provided in Attachment 2, the application of a floating boom provides separation at the surface of the waters
between the sediment storage chamber and the outlet chamber. This effectively captures pollutants such as oils and
greases that float to the surface. Based on laboratory and field testing, Table 1 on Page 3 of the Technical Manual
indicates 90% removal efficiency of Hydrocarbons during emergency spill events.
Also, the proposed Bioretention Basins and Pond are not to become Council assets, rather this will be operated by
the retirement community owner who is responsible for the maintenance and management of these treatment
devices. Managing and replanting of the Bioretention Basins and Pond will be the responsibility of the retirement
community owner.
Based on the above, all areas of road and car parking, except for the road areas in the northern catchment
(Catchment A1 & A2) will be treated by GPT’s. Since Catchment A is only 2.45ha with no significant areas for car
parking a sediment forebay is appropriate.