Minor Change Existing Approval MCU25 0057 01, OPW25 0078 01 & RAL25 0010 01 [As Published]
Officer: Matthew Pinese
Direct Telephone: 07 53296316
Our Reference: MCU25/0057.01
OPW25/0078.01,
RAL25/0010.01
Your Reference: 2026-03-795
12 August 2026
Metricon Homes (Qld) Pty Ltd
C/- Enhance Urban Planning
PO Box 7143
SOUTHPORT PARK QLD 4215
[email protected]
[email protected]
Dear Brendon,
Decision Notice – Minor Change
Planning Act 2016
I refer to your application received on 14 April 2026, requesting a minor change to an existing
development approval. Council decided your requested changes.
Details of the decision are as follows:
1. APPLICATION DETAILS
Application No: MCU25/0057.01, OPW25/0078.01 and RAL25/0010.01
Street address: 9 George Street, Noosaville Qld 4566
Real property description: Lot 8 on RP72243
Planning Scheme: Noosa Plan 2020 (20 March 2026)
2. DECISION DETAILS
The following type of approval was issued on 15 September 2025
• Development Permit for Material Change of Use - Dual occupancy
• Development Permit for Operational Works – Landscaping, Access, Car parking,
Earthworks, Stormwater
• Development Permit for Reconfiguring a Lot – Community Title Subdivision (1 Lot into 3
Lots)
ABN 97.969.214.121 PO Box 141
noosa.qld.gov.au Tewantin QLD 4565
[email protected] 07 5329 6500
Page 1 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 18 pages
Page 2
In relation to the request to make a minor change to the existing approval, Council on 10 August
2026, decided to approve the requested changes. The changes are detailed below.
A. Approve the change.
B. Amend conditions 3 and 32 of the Development Permit for Material Change of Use.
C. Amend condition 1 of the Development Permit for Operational Works.
D. Amend condition 3 of the Development Permit for Reconfiguring a Lot.
E. Correct administrative matters relating to conditions 26, 27, 28 and 29.
F. Re-numbering of the conditions in the Decision Notice resulting from these administrative
changes.
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
4. ASSESSMENT MANAGER CONDITIONS
DEVELOPMENT PERMIT FOR MATERIAL CHANGE OF USE (MCU25/0057)
When Conditions Must Be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
the use commencing, and then compliance maintained at all times while the use continues.
Currency Period
2. This development approval lapses if the use has not happened by 15 September 2031,
unless an application to extend the currency period is approved by Council.
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table/s below.
Plan No. Rev. Plan/Document Name Date
760230 & 760231 - Site Plan prepared by Metricon 20/03/2026
Sheet 02/19
Annotated by Council
760230 & 760231 - Ground Floor Plan prepared by Metricon 20/03/2026
Sheet 03/19
760230 & 760231 - Ground Floor Plan Left prepared by 20/03/2026
Sheet 03A/19 Metricon
760230 & 760231 - Ground Floor Plan Right prepared by 20/03/2026
Sheet 03B/19 Metricon
760230 & 760231 - First Floor Plan prepared by Metricon 20/03/2026
Sheet 04/19
760230 & 760231 - First Floor Plan Left prepared by Metricon 20/03/2026
Sheet 04A/19
760230 & 760231 - First Floor Plan Right prepared by Metricon 20/03/2026
Sheet 04B/19
760230 & 760231 - Roof Plan prepared by Metricon 20/03/2026
Sheet 05/19
Page 2 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 3
Plan No. Rev. Plan/Document Name Date
760230 & 760231 - Elevations prepared by Metricon 20/03/2026
Sheet 06/19
760230 & 760231 - Elevations prepared by Metricon 20/03/2026
Sheet 07/19
760230 & 760231 - Section prepared by Metricon 20/03/2026
Sheet 08/19
760230 & 760231 - Section prepared by Metricon 20/03/2026
Sheet 09/19
760230 & 760231 - Section prepared by Metricon 20/03/2026
Sheet 10/19
Nature and Extent of Approved Use
4. The approved development consists of a Dual occupancy.
Built Form and Development Appearance
5. All air conditioning units or other mechanical equipment must be fully enclosed or screened
such that they are not visible from the street frontages nor adjoining properties.
6. All units where adjoining an external residential allotment are to screen and batten air-
conditioning units to assist with noise mitigation.
7. All deck and balcony areas above ground floor must not be fully enclosed by permanent
fixtures such as shutters, louvres, glass panelling or the like.
8. The development must use muted environmental colour tones that blend with the natural
environment.
Building Height
9. The maximum height of the development must not exceed 8 metres above the natural and
finished ground levels.
10. Certification must be submitted to Council from a Licensed Surveyor which certifies that the
buildings do not exceed the maximum height requirement of this Decision Notice.
Performance Bond
11. Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must
be submitted to Council, to secure performance of all conditions of this approval, prior to pre-
start meeting. The cash bond or trading bank guarantee will be returned on performance of
the conditions of approval less any costs incurred by Council in respect of enforcing
performance of this permit. Council reserves the right to call upon the bond or guaranteed
sum to effect compliance with conditions.
Protection of Privacy
12. To ensure privacy is protected between adjoining properties, the windows located on the
upper level northern building faces of Unit 1 must either:
a. have a minimum windowsill height or 1.7 metres above floor level;
b. be fitted with translucent glazing; or
c. be fitted with a fixed external screen.
Page 3 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 4
13. To ensure privacy is protected between adjoining properties, the windows located on the
upper level southern building faces of Unit 2 must either:
a. have a minimum windowsill height or 1.7 metres above floor level;
b. be fitted with translucent glazing; or
c. be fitted with a fixed external screen.
14. As shown on the Approved Plans, the upper-level terraces located on the western building
face of Units 1 & 2 are to include fixed external screens positioned in such a way to obscure
direct views into the habitable room windows or private open space areas of the adjoining
property. Any fixed external screen(s) must not extend more than 50% of the length of the
balcony
Street Identification
15. The street address of the development from George Street must be clearly visible and
discernible from the primary frontage of the site by the provision of a street number and,
where appropriate, the building name.
Fencing and Walls
16. The combined height of any retaining wall and fence must not exceed 1.8 metres when
located within 6 metres of the front boundary. Any changes in fence height should be tapered
to prevent abrupt transitions.
17. Any street fencing must not exceed 1.8 metres in height, be set back as shown on the
Approved Plans.
18. The area of land between the fence and the front property boundary must be densely
landscaped to screen any fencing from the street.
Community Management Statement
19. Any proposed Community Management Statement required for the development pursuant to
the Body Corporate and Community Management Act 1997 must be submitted to Council for
endorsement at the same time as submission of the Building Format Plan (or similar) to
Council for compliance assessment.
20. All clauses and by-laws of the proposed Community Management Statement must accord
with the requirements of this Decision Notice and, in particular, must include the following
additional clauses:
a. The site includes a stormwater management and water quality treatment system.
b. The stormwater management and water quality treatment system must be maintained
in accordance with the Water by Design (2009) Maintaining Vegetated Stormwater
Assets (Version 1).
c. The full cost of maintaining the system in accordance with the Water by Design (2009)
Maintaining Vegetated Stormwater Assets (Version 1) must be included in the
proposed levies for each dwelling owner/body corporate.
Waste Storage
21. The refuse areas must be of muted environmental tones to reduce the visual impact of the
infrastructure in the streetscape and suitably screened by landscaping where viewed from
the street.
22. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy 9, Waste Management, including an external imperviously paved
area correctly sized for all refuse and recycling containers and suitably screened from public
places and neighbouring properties. A bin wash area is required with a cold-water tap, hose
and drain outlet connected to sewer, via a bucket trap. The drain outlet must be designed to
prevent storm water entry to the sewerage system.
Page 4 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 5
23. Refuse containers must be provided in accordance with the requirements of the
Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
Regulation 2000, for the storage and collection of refuse.
Landscaping Works
24. The development site must be landscaped. The works must be undertaken in accordance
with the PSP2 - Landscape and the Noosa Plan 2020 for that specific area and must include
in particular:
a. the works shown on the Approved Plans
b. vegetated screening of any electrical transformers, bin storage areas and the like from
the road frontage
25. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.
Site Access and Driveways
26. A sealed access driveway must be provided from George Street to all parking and
manoeuvring areas of the development. The works must be undertaken generally in
accordance with SCG Consulting Engineer’s Operational Works Driveway & Access Plan
(00469-OW4.1) and Operational Works Driveway Details Plan (00469-OW4.2) dated March
25 and must include in particular:
a. a driveway crossover in accordance with Council’s standard drawings RS-049, RS-050
and any associated addendum.
Car Parking
27. A minimum of 4 car parking spaces must be provided and marked on the site and generally
in accordance with SCG Consulting Engineer’s Operational Works Driveway & Access Plan
(00469-OW4.1) dated 19/06/2026 and must include in particular:
a. dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities.
Pedestrian Facilities
28. Construct a 1.5 metre wide footpath within the road verge for the entire length of the site’s
frontage to George Street.
Condition 28 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Stormwater Drainage
29. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken generally in accordance with SCG Consulting
Engineer’s Operational Works Stormwater Management Plan (00469-SW1.1) dated 19 June
2026 and must include in particular:
a. 3,000L of on-site rainwater retention per dwelling.
Condition 29 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Services
30. Underground reticulated electricity and telecommunication services must be provided to
each lot/unit in accordance the standards and requirements of the relevant service provider.
31. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
Page 5 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 6
32. Certification must be submitted to Council from all relevant service providers (Energex, NBN
and Unitywater) which certifies that the development has met the requirements of this
Decision Notice and all applicable legislation at the time of construction.
Earthworks and Retaining Walls
33. All earthworks and associated batters/retaining structures, both above and below ground
level, both temporary and permanent, must be undertaken in accordance with the conditions
of this approval, be generally in accordance with SCG Consulting Engineer’s Operational
Works Earthworks Plan (00469-OW3.1) dated March 25 119/06/2026 Rev B, and contained
entirely within the subject site unless written permission from the respective landowner(s) is
provided to Council.
34. All retaining walls must be designed and constructed in accordance with the planning scheme
and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
safety fence.
Damage to Services and Assets
35. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
DEMOLITION WORK
Codes of Development
36. Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
solutions as contained in the Waste Management Code and Water Quality and Drainage
Code of the Noosa Plan 2020.
Demolition Works
37. Demolition must be undertaken in a manner that causes no detrimental effect upon the
amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
in accordance with the nuisance provisions of the Environmental Protection Act 1994.
Waste Management
38. Adequate area must be provided on-site for the collection and separate storage of recyclable,
non-recyclable, vegetative and hazardous materials in their specific waste streams during
removal or demolition works.
39. All waste materials must be removed from the site to avoid causing unhealthy conditions,
with the site left clean, tidy and free from any debris.
Water Quality and Drainage
40. Erosion and sediment control is to be undertaken in accordance with the requirements of the
Water Quality and Drainage Code of the Noosa Plan. Measures are to be installed and/or
maintained until soils are stabilised by vegetation or sealed.
NOTE: It is an offence under the Environmental Protection Act 1994 to deposit or potentially
allow litter, waste, soil, or other contaminants to enter a waterway or storm water drainage
system (e.g. roadside gutter).
Page 6 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 7
Health and Safety
41. All building materials containing asbestos, including asbestos cement sheeting or roofing and
lagging, are removed from the building prior to demolition or relocation.
42. Removal of building materials containing asbestos must be undertaken by a licensed
asbestos removalist.
43. Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
requires a licensed asbestos removalist to give notice to Workplace Health and Safety
Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
commences. Notification must be made using Form 65: Notification of licensed asbestos
removal work, demolition work or emergency demolition.
44. All building materials containing asbestos products are wrapped and disposed of in
accordance with the Public Health Regulation 2006 and the Environmental Protection
Regulation 2008.
Note: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
businesses that transport asbestos waste, and landfills that accept this waste.
Plumbing and Drainage
45. It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
demolition of a building, the existing sanitary drain upstream from the connection point for a
service provider’s sewerage system must be sealed watertight. This work is deemed as
notifiable Work and must be carried out by a suitably licenced plumber who must submit an
As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
Construction Commission) within 10 days of completing the work.
Page 7 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 8
DEVELOPMENT PERMIT FOR OPERATIONAL WORKS (OPW25/0078)
Approved Plans
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
00469-OW3.1 B Earthworks Plan prepared by SCG 19/06/2026
Consulting Engineers
00469-OW4.1 C Driveway and Access Plan prepared by 19/06/2026
SCG Consulting Engineers
00469-OW4.2 B Driveway Details prepared by SCG 19/06/2026
Consulting Engineers
00469-SW1.1 D Stormwater Management Plan prepared by 19/06/2026
SCG Consulting Engineers
090226 V2 Hardscape Plan prepared by Metricon 9/02/2026
1 of 3
090226 V2 Planting Plan prepared by Metricon 9/02/2026
2 of 3 Annotated by Council
090226 V2 Details Plan prepared by Metricon 9/02/2026
3 of 3
Currency Period
2. The Currency Period for this development approval lapses if the development has not
substantially started by 15 September 2027 unless an application to extend the currency
period is approved by Council.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
3. All necessary approvals from external service providers (e.g. Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
4. Copies of the approved plans, duly signed by the consultant Registered Professional
Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer
Construction at the “pre start” meeting.
5. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
6. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
7. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Landscape works;
Page 8 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 9
c. Erosion and sediment control works;
d. Other relevant parties
8. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD)
b. provision for safe pedestrian access across the frontage of the site both during daily
construction and after daily construction has ceased.
9. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
10. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
11. Prior to requesting a prestart meeting:
a. Receipt of amended plans (refer to Condition 1) for approval.
DURING CONSTRUCTION
Engineering
12. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
13. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
14. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice
b. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines
c. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site
Works within Road Reserve/Reinstatement
15. Safe pedestrian and vehicle access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out construction
works, Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
16. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
17. The verge is to be modified such that the maximum crossfall for the verge is 5%, except in
the location of a pathway where the maximum crossfall is to be 2.5%.
Page 9 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 10
18. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Pathways
19. All pathways must be constructed in accordance with the following requirements:
a. All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065.
b. Provision must be made for disabled access at all kerb crossings associated with
pathways, in accordance with Council's current standards.
c. All paths must have a slip resistant surface.
d. Expansion and contraction joints must provide a flush finish. Installation of joints by
saw cutting is preferred to ensure a smooth ride for cyclists.
e. The required work includes any modifications to ensure the footpath finishes flush with
all existing service covers and the like, or alternatively these services are raised or
altered, so as not to create a pedestrian safety hazard.
20. Pathways must:
a. terminate in a manner that ensures smooth transition to existing surfaces for public
safety.
b. be designed and constructed to comply with the Disability Discrimination Act (DDA),
Access to Premises Standard, Austroads and relevant sections of AS1428 Design for
access and mobility.
Site Access and Driveways
21. Driveway crossovers must be constructed in accordance with council’s Standard Drawings
RS-049, RS-050 and RS-051 and any associated addendum.
22. Any existing unnecessary or redundant property accesses must be removed, and the kerb,
footpath and verge area reinstated to match the existing footpath and/or verge treatments.
Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
or turf, and must be maintained by the developer until established.
23. The following must be complied with during the construction of the required
crossover/driveway:
a. The driveway surfacing must consist of either an approved hot mixed asphaltic
concrete or patterned/plain concrete.
b. The driveway must be constructed so as not to concentrate stormwater runoff onto
neighbouring properties.
c. Underground service conduits for water supply, electricity and any other services must
be provided as part of the access driveway
d. Where there is an existing pedestrian path, a matching crossfall must be provided for
the driveway on the alignment of the path, for the full width of the path.
e. The property access must be located a minimum of 1m clear of existing power poles,
streetlights or other signage. The developer is responsible for any necessary relocation
of existing services to provide this clearance and must contact the relevant service
authorities and comply with their requirements in relation to these works.
Page 10 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 11
Earthworks and Retaining Walls
24. All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
on Earthworks for Commercial and Residential Development, with geotechnical testing
undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as
defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
uniformity of fill shall be provided by a RPEQ and submitted to Council prior to Council signing
the Plan of Survey.
25. All earthworks and associated batters/retaining structures, both above and below ground
level, both temporary and permanent, must be contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to Council.
26. Fall protection must be provided to retaining walls that are over 1m high.
27. Slope and batters are a maximum grade of:
a. 1 in 6 where in proximity to waterbodies
b. 1 in 4 for grassed areas.
c. 1 in 3 for planted areas.
d. 1 in 2 for combined structural engineering and planting solutions.
Stormwater Drainage
28. Appropriate scour protection must be provided at the outlet of all stormwater pipes including
temporary outlets.
29. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (e.g. by blocking or interfering with natural overland flows).
30. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
31. Prior to the completion of the development, all site surfaces must be effectively stabilised
using methods which have achieved effective short-term stabilisation and which will continue
to achieve effective stabilisation in the medium- to long-term (refer to E&SC Advisory Notes).
For the purpose of this condition, an effectively stabilised surface is defined as one that does
not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion
or lead to sedimentation, or lead to water contamination.
Erosion and Sediment Control
32. Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
Regulation 2019) must not be released from the site or to waters within the site, or be likely
to be released should rainfall occur, unless all reasonable and practicable measures are
taken to prevent or minimise the release and concentration of contamination.
33. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system, natural waterways, any downstream stormwater filtration
system or adversely impacting on other properties. The sediment and erosion control design
and measures have NOT been approved, it is the site's Supervising Engineer who is
responsible for ensuring that the sediment and erosion control measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
practise" methods,
b. Been revised by an RPEQ or CPESC to address the issues raised by changes in the
projected construction schedule and/or methods,
c. Been revised to address predicted rainfall events, and
d. Achieve the desired environmental outcomes.
Page 11 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 12
34. Council may request further controls to be installed should the implemented measures be
found inefficient.
35. The erosion and sediment control measures must be designed, installed and maintained in
accordance with the supervising engineer instructions and the current best practice
standards * (Refer to Advisory Note).
36. The developer must ensure non-essential exposure of soil is prevented by restricting the
extent of disturbance and minimising the duration of soil exposure to adverse weather
conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
to rainfall occurring.
37. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
machinery. It is essential to implement appropriate approved erosion and sediment control
measures throughout the site during all phases of construction including vehicle shakedown
pad/grid (or similar) at the access to the construction site. Where sediments or other
contaminants are deposited on a road, they must be removed so as not to enter Council’s
drainage system or waterways.
38. Prior to the completion of the development and commencement of use, all site surfaces must
be effectively stabilised using methods which have achieved effective short-term stabilisation
and which will continue to achieve effective stabilisation in the medium to long-term. For the
purpose of this condition, an effectively stabilised surface is defined as one that does not, or
is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
lead to sedimentation, or lead to water contamination.
Vegetation Clearing
39. Removal of trees and vegetation must be undertaken by a qualified person* and must
include:
a. No damage to vegetation for retention.
b. Legal disposal of all removed vegetation and debris.
Fauna Management
40. Prior to felling or pruning, all trees are to be checked for wildlife (i.e. koalas, possums, birds
etc.) If wildlife is present, the tree vegetation must not be felled or pruned until the wildlife
has left vegetation or has been relocated by a qualified fauna spotter catcher.
*(Refer to Advisory Note)
Landscape Works
41. Landscape works must be supervised, undertaken and certified by qualified persons*. All
works must be completed in accordance with this Decision Notice.
*(Refer to Advisory Note)
42. Where damage occurs to any Council asset as a result of the development works, it must be
repaired immediately where it creates a hazard that presents risk to person or property. Other
damage must be repaired prior to completion of works.
43. Street trees must:
a. Meet AS2303 Tree stock for landscape use.
b. Be located in accordance with engineering requirements for safe vehicle and
pedestrian sight lines.
44. The finished level of all mulch in garden beds and landscaped medians is to be a minimum
of 50mm below the level of the adjacent top of kerb. All landscaping is to be constructed in
accordance with Council’s Planning Scheme Policy PSP2 Landscaping.
Page 12 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 13
45. Suitable root barriers must be installed where proposed trees are adjacent to paths,
pavement etc in accordance with Council’s Planning Scheme Policy PSP2 Landscaping.
46. An inspection is to be carried out with the relevant Council officers, the Contractor and
Supervising Engineer after road centrelines have been established, and prior to clearing
being carried out. This inspection is to deal with the limits of clearing to be carried out for this
development. This meeting is to take place prior to the “Pre-start” meeting.
Damage to Services and Assets
47. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets must
first be referred to the relevant service authority for approval.
FOLLOWING CONSTRUCTION / PRIOR TO THE COMMENCEMENT OF THE USE / COUNCIL
SIGNING THE PLAN OF SURVEY
Certification
48. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit.
Supervision/Certification
49. Prior to commencement of use the following (prepared by respective qualified persons* and
certifying compliance with approvals) must be submitted to Council:
a. Landscaping certification confirming all works have been constructed in accordance
with conditions of approval.
*(Refer to Advisory Note)
Page 13 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 14
DEVELOPMENT PERMIT FOR RECONFIGURING A LOT (RAL25/0010)
When Conditions Must Be Complied With
1. Unless otherwise stated, all works required by the conditions of this Decision Notice must be
completed prior to the lodgement of a Plan Seal application.
Currency Period
2. This development approval lapses if the requirements of the conditions have not been
completed and an application for plan seal is not lodged with Council by 17 September 2029
unless an application to extend the currency period is approved by Council.
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table/s below.
Plan No. Rev. Plan/Document Name Date
760230 & 760231 - Subdivision Plan prepared by Metricon 20/03/2026
20/19
4. All lot numbering on the subdivision plan to be submitted to Council for compliance
assessment must remain as shown on the Approved Plans.
Boundary Encroachments
5. Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which
certifies that:
a. all constructed access and roadworks (including associated fill batters and retaining
walls) are fully contained within a dedicated reserve or registered easement.
b. all utility services and connections (eg. electricity, telecommunications, water,
sewerage) are wholly located within the lot they serve or alternatively included within
an easement.
c. all dams (including ponded water, dam walls and associated spillway structures) are
wholly located within the boundaries of a single lot.
d. all retaining walls and structures are fully contained within the lot they retain unless
otherwise required by condition.
e. any fill, including fill batters, are wholly contained within the subject site and not on
adjacent properties.
f. for the community title scheme, the road pavement changes required by this Decision
Notice accurately demarcate the boundaries of the public and private land.
Water & Sewer Connections
6. An underground connection to reticulated water and sewerage must be provided to each
Multiple Dwelling in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
must be submitted to Council that certifies an underground connection to reticulated water
and sewerage has been provided to each Multiple Dwelling.
Services
7. Underground reticulated electricity and telecommunication services must be provided to
each lot in accordance with an approval for Operational Works and the standards and
requirements of the relevant service provider.
Page 14 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 15
8. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
9. Certification must be submitted to Council from all relevant service providers (Energex, NBN)
which certifies that the development has met the requirements of this Decision Notice and
all applicable legislation at the time of construction.
Community Management Statement
10. Any proposed Community Management Statement required for the development pursuant to
the Body Corporate and Community Management Act 1997 must be submitted to Council for
endorsement at the same time as submission of the Building Format Plan (or similar) to
Council for compliance assessment.
11. All clauses and by-laws of the proposed Community Management Statement must accord
with the requirements of this Decision Notice and, in particular, must include the following
additional clauses:
a. The site includes a stormwater management and water quality treatment system.
b. The stormwater management and water quality treatment system must be maintained
in accordance with the Water by Design (2009) Maintaining Vegetated Stormwater
Assets (Version 1).
c. The full cost of maintaining the system in accordance with the Water by Design (2009)
Maintaining Vegetated Stormwater Assets (Version 1) must be included in the
proposed levies for each dwelling owner/body corporate.
5. REFERENCE DOCUMENTS
Not applicable.
6. REFERRAL AGENCIES
Not applicable.
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Aboriginal Cultural Heritage Act 2003
1. There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
carries out an activity must take all reasonable and practicable measures to ensure the
activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
duty of care. Substantial monetary penalties may apply to individuals or corporations
breaching this duty of care. Injunctions may also be issued by the Land and Resources
Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
Equitable Access and Facilities
2. The plans for the proposed building work have NOT been assessed for compliance with the
requirements of the National Construction Code - Building Code of Australia (Volume 1) as
they relate to people with disabilities. Your attention is also directed to the fact that in addition
to the requirements of the National Construction Code as they relate to people with
disabilities, one or more of the following may impact on the proposed building work:
a. the Disability Discrimination Act 1992 (Commonwealth);
Page 15 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 16
b. the Anti-Discrimination Act 1991 (Queensland); and
c. the Disability (Access to Premises – Buildings) Standards.
Advertising Devices
3. All Advertising Devices must comply with Schedule 10 of Subordinate Local Law No.1
(Administration) 2015 including both temporary and permanent signage. All freestanding,
pylon or pole signs or signage that is illuminated requires approval from Council prior to being
installed. All signage identified in s6 of Schedule 10 of Subordinate Local Law No. 1 is
prohibited from being erected in the Shire.
Infrastructure Charges
4. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges
Performance Bond Agreement
5. An applicant for a development application may make an agreement with an assessment
manager, referral agency or other person to establish the responsibilities, or secure the
performance, of a party to the agreement about a development condition.
Development Compliance Inspection
6. Prior to the commencement of the use, please contact Council's Development Assessment
Branch to arrange a Development Compliance Inspection.
Building and Construction Industry (Portable Long Service Leave) Levy
7. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.
Retention of Existing Trees
8. The existing trees on adjoining properties must be retained and protected during construction
wherever achievable. To avoid doubt, this advisory note is not intended to exclude the
operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following
construction of the development which is the subject of this development approval.
Removal of Existing Trees and Vegetation
9. Stockpiling mulch to the appropriate volume and separation is required for fire mitigation as
well as optimum weed seed sterilisation.
Qualified Person
10. Qualified Person, for the purpose of:
a. Supervising landscape works and preparing a landscape certification, is considered to
be a landscape architect, landscape designer or horticulturist with a minimum of three
years current experience in the field of landscape design.
b. Undertaking landscape construction and establishment works is considered to be a
person with five years current experience in commercial landscape construction
projects.
c. Undertaking, supervising tree works and preparing arboriculture certification, is
considered to be a person with a minimum three years current experience in tree
protection, hazard identification/mitigation and Specifying Trees – a guide to
assessment of tree quality (NATSPEC) assessment and either:
i. International Society of Arboriculture (ISA) certification; or
ii. A Diploma of Arboriculture.
Page 16 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 17
d. Managing Fauna protection is considered to be a certified Fauna Spotter
Catcher.
Landscape Works
11. The applicant must pay the re-inspection fee in accordance with Council's Fees and Charges
Register where:
a. An inspection revealed that any constructed rehabilitation/landscape works do not
comply with the conditions of the Decision Notice, Approved Plans and or Approved
Documents
b. Certification is submitted to Council falsely stating that works comply with the approved
plans, documents and or conditions of the Decision Notice.
Biosecurity Act 2014 – Fire Ant Control
12. Developers must remain vigilant for the presence of fire ants. Under the Biosecurity Act 2014,
individuals and businesses are responsible for ensuring that they follow the movement
controls for specific organic materials to help prevent the spread of fire ants within South
East Queensland’s fire ant biosecurity zones. Movement of a fire ant carrier from within a fire
ant biosecurity zone may need a biosecurity instrument permit. More information is available
on https://www.fireants.org.au/treat/business-andindustry/movement-controls.property
notes
8. VARIATION APPROVAL DETAILS
Not applicable.
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Building Works All building work.
10. SUBMISSIONS
Not applicable.
11. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.
12. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available online at
www.noosa.qld.gov.au or at Council Offices.
Yours faithfully
Matthew Pinese
Development Planner | Development Assessment
Development & Regulation
Enc: Appeal Rights
Approved Plans/Documents
Page 17 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 18
DECISION NOTICE HISTORY
• Original Decision Notice -15 September 2026.
• Decision Notice - Minor MCU25/0057.01, OPW25/0078.01 &
RAL25/0010.01) – 10 August 2026, with an amendment to
conditions 3 & 32 of MCU and amend condition 1 of OPW and
amend condition 3 of RAL; correct administrative conditions 26-29;
re-numbering due to administrative changes.
Page 18 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
Page 19
Appeal Rights
PLANNING ACT 2016 & PLANNING REGULATION 2017
Chapter 6 Dispute resolution (3) The appellant or, for an appeal to a tribunal, the registrar must,
within the service period, give a copy of the notice of appeal to –
Part 1 Appeal rights
(a) the respondent for the appeal; and
229 Appeals to tribunal or P&E Court
(b) each co-respondent for the appeal; and
(1) Schedule 1 of the Planning Act 2016 states –
(c) for an appeal about a development application under schedule
(a) Matters that may be appealed to –
1, table 1, item 1 – each principal submitter for the
(i) either a tribunal or the P&E Court; or development application; and
(ii) only a tribunal; or (d) for and appeal about a change application under schedule 1,
table 1, item 2 – each principal submitter for the change
(iii) only the P&E Court; and
application; and
(b) The person-
(e) each person who may elect to become a co-respondent for the
(i) who may appeal a matter (the appellant); and appeal, other than an eligible submitter who is not a principal
submitter in an appeal under paragraph (c) or (d); and
(ii) who is a respondent in an appeal of the matter; and
(f) for an appeal to the P&E Court – the chief executive; and
(iii) who is a co-respondent in an appeal of the matter; and
(g) for an appeal to a tribunal under another Act – any other
(iv) who may elect to be a co-respondent in an appeal of the
person who the registrar considers appropriate.
matter.
(4) The service period is –
(2) An appellant may start an appeal within the appeal period.
(a) if a submitter or advice agency started the appeal in the P&E
(3) The appeal period is –
Court – 2 business days after the appeal has started; or
(a) for an appeal by a building advisory agency – 10 business
(b) otherwise – 10 business days after the appeal is started.
days after a decision notice for the decision is given to the
agency; or (5) A notice of appeal given to a person who may elect to be a co-
respondent must state the effect of subsection (6).
(b) for an appeal against a deemed refusal – at any time after the
deemed refusal happens; or (6) A person elects to be a co-respondent by filing a notice of election,
in the approved form, within 10 business days after the notice of
(c) for an appeal against a decision of the Minister, under chapter
appeal is given to the person.
7, part 4, to register premises or to renew the registration of
premises – 20 business days after a notice us published under 231 Other appeals
section 269(3)(a) or (4); or
(1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
(d) for an appeal against an infrastructure charges notice – 20 the Supreme Court decides a decision or other matter under this
business days after the infrastructure charges notice is given Act is affected by jurisdictional error, the decision or matter is non-
to the person; or appealable.
(e) for an appeal about a deemed approval of a development (2) The Judicial Review Act 1991, part 5 applies to the decision or
application for which a decision notice has not been given – matter to the extent it is affected by jurisdictional error.
30 business days after the applicant gives the deemed
(3) A person who, but for subsection (1) could have made an
approval notice to the assessment manager; or
application under the Judicial Review Act 1991 in relation to the
(f) for any other appeal – 20 business days after a notice of the decision or matter, may apply under part 4 of that Act for a
decision for the matter, including an enforcement notice, is statement of reasons in relation to the decision or matter.
given to the person.
(4) In this section –
Note – decision includes-
See the P&E Court Act for the court’s power to extend the appeal
(a) conduct engaged in for the purpose of making a decision; and
period.
(b) other conduct that relates to the making of a decision; and
(4) Each respondent and co-respondent for an appeal may be heard
in the appeal. (c) the making of a decision or failure to make a decision; and
(5) If an appeal is only about a referral agency’s response, the (d) a purported decision; and
assessment manager may apply to the tribunal or P&E Court to
(e) a deemed refusal.
withdraw from the appeal.
non-appealable, for a decision or matter, means the decision or
(6) To remove any doubt. It is declared that an appeal against an
matter-
infrastructure charges notice must not be about-
(a) is final and conclusive; and
(a) the adopted charge itself; or
(b) may not be challenged, appealed against, reviewed, quashed,
(b) for a decision about an offset or refund-
set aside or called into question in any other way under the
(i) the establishment cost of trunk infrastructure identified in Judicial Review Act 1991 or otherwise, whether by the
a LGIP; or Supreme Court, another court, a tribunal or another entity; and
(ii) the cost of infrastructure decided using the method (c) is not subject to any declaratory, injunctive or other order of
included in the local government’s charges resolution. the Supreme Court, another court, a tribunal or another entity
on any ground.
230 Notice of appeal
232 Rules of the P&E Court
(1) An appellant starts an appeal by lodging, with the registrar of the
tribunal or P&E Court, a notice of appeal that- (1) A person who is appealing to the P&E Court must comply with the
rules of the court that apply to the appeal.
(a) is in the approved form; and
(b) succinctly states the grounds of the appeal. (2) However, the P&E Court may hear and decide an appeal even if
the person has not complied with the rules of the P&E Court
(2) The notice of appeal must be accompanied by the required fee.
Page 19 of 19