Minor Change Existing Approval MCU25 0057 01, OPW25 0078 01 & RAL25 0010 01 [As Published]
23. Refuse containers must be provided in accordance with the requirements of the
Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
Regulation 2000, for the storage and collection of refuse.
Landscaping Works
24. The development site must be landscaped. The works must be undertaken in accordance
with the PSP2 - Landscape and the Noosa Plan 2020 for that specific area and must include
in particular:
a. the works shown on the Approved Plans
b. vegetated screening of any electrical transformers, bin storage areas and the like from
the road frontage
25. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.
Site Access and Driveways
26. A sealed access driveway must be provided from George Street to all parking and
manoeuvring areas of the development. The works must be undertaken generally in
accordance with SCG Consulting Engineer’s Operational Works Driveway & Access Plan
(00469-OW4.1) and Operational Works Driveway Details Plan (00469-OW4.2) dated March
25 and must include in particular:
a. a driveway crossover in accordance with Council’s standard drawings RS-049, RS-050
and any associated addendum.
Car Parking
27. A minimum of 4 car parking spaces must be provided and marked on the site and generally
in accordance with SCG Consulting Engineer’s Operational Works Driveway & Access Plan
(00469-OW4.1) dated 19/06/2026 and must include in particular:
a. dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities.
Pedestrian Facilities
28. Construct a 1.5 metre wide footpath within the road verge for the entire length of the site’s
frontage to George Street.
Condition 28 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Stormwater Drainage
29. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken generally in accordance with SCG Consulting
Engineer’s Operational Works Stormwater Management Plan (00469-SW1.1) dated 19 June
2026 and must include in particular:
a. 3,000L of on-site rainwater retention per dwelling.
Condition 29 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Services
30. Underground reticulated electricity and telecommunication services must be provided to
each lot/unit in accordance the standards and requirements of the relevant service provider.
31. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
Page 5 of 19
Document Set ID: 25050577
Version: 5, Version Date: 12/08/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.