Not Properly Made Submission (Duplicate) Jennifer Sadler MCU12/0216

of 2

Page text shows just the words. Original shows the document exactly as it was published.

Jennifer Sadler
181 Forest Acres Drive
Lake Macdonald 4563

8 May 2013

Mr Marcus Brennan,
Assessment Manager
Sunshine Coast Council
Locked bag 72
Sunshine Coast Mail Centre 4560

Submission re MCU12/0216

Dear Mr Brennan,

I wish to put forward my comments for you to consider in the assessment of the above
Development Application for a Material Change of Use at 271 Lake Macdonald Drive.

1. The Notice of Commencement is attached to the fence at Gate 4 of the brickworks
   site on Lake Macdonald Drive.
   It is well back from the road next to other signs on the fence and has nothing to dis-
   tinguish it as being a new sign that would be of interest to anyone other than people
   who worked at the site.
   I believe notices alerting the public to a new or changed development must be
   prominently displayed and this sign is not.
   By the time the public were aware that there was an MCU lodged at Council for an
   increase in extraction of clay from the clay pit on Kennedy Drive to be transported
   to the clay pits on Lake Macdonald Drive the ’comment period’ was already half
   over not allowing time for proper research into the impacts on locals.
   Further, locals who would be most impacted by the change in use (those on Hoy
   Rd, Lake Ridge Court and Racehorse Lane) would have no reason to ever drive by
   the brickworks and so would never have the opportunity to see the sign even if it
   were well displayed.
2. In the Development Application Part 2 of 2 ‘Traffic Assessment’ by TTM Consulting
   (Sunshine Coast) Pty Ltd. It states:
   2.2 Haulage Profile
    ‘TTM have been advised that the proposed rehabilitation of Neales Quarry and
    White Pit Quarry will involve the extraction of up to 900,000 tonnes (0.90Mt) over
    a 2 year period. It is understood that the haulage vehicle will be a truck and dog
    with a payload of 30 tonnes. Over this period it is anticipated that up to 30,000
    heavy vehicles will enter and exit the subject site with an anticipated maximum of
    50 heavy vehicles per day’.
  It states in the Information Request Response dated April 2, 2013
    ‘The Traffic Impact Assessment Report prepared by TTM Consulting Pty Ltd,
    included as Attachment 7 of the Planning Assessment Report submitted to Coun-
    cil, identifies that a total of 60,000 vehicle movements over the life of the project
    (i.e. 2 years) for the proposed operations will be required to enter and exit the
    Site in order to haul the extracted material to the receiving sites (i.e. Neales
Log in to download the original file

Not Properly Made Submission (Duplicate) Jennifer Sadler MCU12_0216.pdf · 21 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 1 page

Page 2

    Quarry and White Pit Quarry). This represents 30,000 movements per year x 2
    years.
This is a very serious discrepancy, and because of it, the correctness of the Traffic Im-
pact study is in doubt.
I believe that 50 trucks a day entering and exiting the site 6 days a week (6am to 6pm
Monday-to-Friday and 7am to 3pm on Saturdays) will cause serious disturbance to resi-
dents living along the haulage route from noise and dust, as well as hold ups to these
residents and residents living further out in the Forest Acres area when travelling into Co-
oroy. Lake Macdonald Drive is only a two lane road. The impact of 100 trucks a day
would of course be double that of 50.
In the next paragraph ((b) Internal and External Vehicle Movements at the Brickworks
Factory Site) states
   ‘CSR have advised that this is less than the vehicle traffic movements for the past
   mining lease operations associated with the former brickworks operation.
   CSR have advised that approximately 32,400 vehicle movements were generated
   by the brickworks operation over a 1 year period (for the past operations) for
   haulage of material into the brickworks factory site and delivery of brick products
   to the market.
   As such, the traffic volumes for the proposed operations are less than the
   traffic volumes for the past operations associated with the brickworks factory’.
In the two weeks available for research into the Material Change of Use I have been un-
able to ascertain if the brickworks, while in operation had 32,400 vehicle movements per
year. Long term residents that I spoke to believe that this is not correct and that the vol-
ume of traffic from the brickworks was much less. I have tried to get accurate information
from Council without success at this stage.
Also it isn’t clear what the pay load of the trucks or if they had a dog attached, were run-
ning when the brickworks were in operation. This makes it hard to make an accurate
comparison.
3. Other suggestions for your consideration.
   Anecdotally I have heard that there is now what is thought to be clay in 6 Mile
   Creek behind Old Coach Way, Lake Macdonald. This is possibly because of the
   movement of clay from a CSR mining lease elsewhere in Cooroy that is happen-
   ing at present. Six Mile Creek is populated by platypus and an impact assessment
   should be conducted on the Six Mile Creek to ascertain how well the platypus will
   survive if there is further impact to their environment if the MCU is approved.
   There is clay on Lake Macdonald Drive now. Clay on the road is a serious prob-
   lem for vehicles, both car and motorbike. Action should be included in a success-
   ful application to prevent clay being spilled on the road and when it is, cleaned up
   at CSRs expense.
Thankyou for your consideration




Jennifer Sadler

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.