PRESENTATION - Jade Oakley x CR - Noosa Concept Final 24-4-25_Optimized · EXE25/0029

of 39

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

BUDGET                                                                                   TIMELINE

 Fees                                                                                    Stage/Description                           Duration    Completion

 Jadel Oakley - Artist Fee + Community Engagement                            $40,000

 Creative Road - Curatorial + Project Management                              $25,000    PROJECT INCEPTION
                                                                SUBTOTAL     $65,000     Artist Agreement Executed                   Milestone   August, 2025
 Artwork Budget

 Detailed Design                                                                         DESIGN DEVELOPMENT
 Detailed Design                                                              $24,000    Community Engagement                        1 week      September, 2025
 Engineering Review + Certification                                            $8,000    Developed Design Period                     8 weeks     November, 2025
 Fabrication
                                                                                         Final Design Presentation + Approval        Milestone   November, 2025
 Mould Fabrication                                                            $14,500
                                                                                         3D Model Development                        2 weeks     December, 2025
 Boat Frame + Base Footing                                                    $10,000

 Concrete Supply + Finishing                                                  $15,000
                                                                                         Allowance for Christmas NY Shutdown         4 weeks     January, 2026
 Packing + Transport                                                           $9,000

 Installation
                                                                                         FABRICATION
 Footings, Earthworks, Crane Hire + Labour                                    $17,500
                                                                                         Mould Fabrication                           4 weeks     February, 2026
 SWMS, Traffic Management + Artwork Installation                               $2,000
                                                                                         Steel Fabrication                           3 week      March, 2026
                                                               SUB-TOTAL     $100,000
                                                                                         Concrete Supply + Finishing                 4 weeks     April, 2026
 Project Costs
                                                                                         Artwork inspection (80%)                    Milestone   April, 2026
 Admin                                                                         $4,000
                                                                                         Installation Plan + SWMS                    Milestone   April, 2026
 Travel + Accom                                                                $4,000

 Audio Recording + Editing                                                      $1,100
                                                                                         INSTALLATION
 Photography                                                                   $2,250
                                                                                         Ground Treatment Prep + Concrete Footings   2 weeks     May, 2026
 Maintenance Manual                                                            $2,250
                                                                                         Artwork Installation                        1 week      May, 2026
 Insurance                                                                     $1,000
                                                                                         Practical Completion & Maintenance Manual   Milestone   May, 2026
                                                               SUB-TOTAL      $14,600
                                                                                         Artwork Launch + Documentation              1 Week      June, 2026


                                                     GRAND SUB-TOTAL         $179,600

                                                            CONTINGENCY       $15,850

                                                        TOTAL excl. GST      $195,450

                                                                      GST     $19,545

                                                            TOTAL inc. GST   $214,995


* Exclusions: Lighting Design + Supply, Attribution Signage


Noosa Council CityDeal Public Art Initiative | April 2025                                                                                                Jade Oakley x Creative Road   29

Used in these records

About this file

File size
5.8 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

PRESENTATION - Jade Oakley x CR - Noosa Concept Final 24-4-25_Optimized.pdf · 5.8 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.