3.   Construction Management

3.1 Approach

       The major external constraints on the project are:

          • Maintaining smooth traffic and pedestrians flow with minimal disruptions to the
               residents in Avocet Parade;

          • Undertaking works with minimal impact on neighbours, in particular, adjoining
               residential properties

       Upon commencement, our project team’s immediate tasks will be to:

          • Locate a project office, site accommodation and facilities,

          • Assess the existing structure on-site and prepare for removal,

          • Confirm the locations of existing services and obtain all necessary permits and licences
               and approvals, and

          • Arrange for the installation of temporary services – power, water and sewer to service
               the site works and the amenities.

3.2 Approvals

       A Negotiated Decision Notice has been issued for the proposed development – Other
       Change Approval 51901.4274.02.

       It is proposed that a Building Approval (BA) will be obtained from a qualified Private Certifier
       (PC). It is proposed that the BA will be approved in the following sequence:

          • Demolition and site prep works.

          • Building and renovation work to existing units;

          • Structural works for Ground & Level 1 including pool;

          • Structural works for Level 2

3.3 Site Security

       The site will be secured using appropriate construction fencing and signage for authorised
       personal only. All visitors to the site will be required to report to the construction manager, and
       will be appropriately inducted and registered in a visitor’s logbook.

3.4 Public / Worker Safety

       All site staff and subcontractors will be required to complete a site specific induction before
       commencing work on site. The induction will cover aspects relating to safety and amenity;
       including access, emergency evacuation procedures, location of first aid facilities, location of
       amenities, site hours, material handling, noise and dust policies and environmental


RG Strategic                               Construction Management Plan                                 5

Used in these records

About this file

File size
1.2 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Avocet Pde OPW - App C CMP.pdf · 1.2 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.