4. Construction Methodology

4.1 Demolition and Excavation

       A Waste Management Plan will be submitted to Council for approval with the Final
       Construction Management Plan at the Pre-Start Meeting. Demolition and excavation of any
       construction materials will be in accordance with the Waste Management Plan.

4.2 Construction Sequence and Planning

       The locations and types of plant may vary depending on the results of more detailed planning
       as the design solidifies and the availability of plant is firmed up. There will be 3 distinct phases
       requiring different material handling logic to construct the building efficiently and minimise
       impact on surrounding streets and neighbours.

       The phases are:

         Phase 1: Site establishment; demolition; excavation and pile installation,

         Phase 2: Structure Phase, and

         Phase 3: Finishes and external works

       Each phase will not happen in isolation. Phase 2 and 3 will happen simultaneously once the
       structure is sufficiently complete to allow the finishes trades to commence on all levels. A
       Construction Gantt Chart will be provided to Council at the Pre-Start Meeting once a Building
       Contractor has been appointed.

4.3 Rubbish Removal

       A designated waste collection area will be provided for on site that does not receive a
       substantial amount of runoff from upland areas and does not drain directly to water body.

       Rubbish will be removed from site by a licenced waste contractor ensuring that it is managed
       to comply with Noosa Council and their contractor’s requirements. It will be taken to the to a
       transfer facility.

       Disposal of waste collection bins are to be clearly marked '"conventional waste”, "recyclable"
       and "regulated waste".

       The Principal Contractor will ensure that all containers are fitted with lids and that waste
       collection is scheduled to prevent the containers from overfilling.




RG Strategic                               Construction Management Plan                                  8

Used in these records

About this file

File size
1.2 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Avocet Pde OPW - App C CMP.pdf · 1.2 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.