7. Fix the problem. Tell the customer what solution you can offer and make sure they
understand. If they accept the solution, act straight away and resolve the matter quickly
and efficiently.
3.8 Existing Infrastructure
Existing infrastructure will be protected during construction. The selected Contractor shall
clean off any debris deposited on the road. Dial Before You Dig enquiries will be undertaken
prior to all excavation works.
3.9 Fencing
2 metre high temporary fencing will secure the site. Security gates will be used on all access
points onto the site.
RG Strategic Construction Management Plan 7