Original source · versioned page text
2015-06-04 Ordinary Meeting Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
ORDINARY MEETING AGENDA 4 JUNE 2015
GENERAL COMMITTEE RECOMMENDATIONS
1 JUNE 2015 - Crs Frank Wilkie (Chair), Bob Abbot, Sandy Bolton, Joe Jurisevic,
Frank Pardon, Noel Playford and Tony Wellington
1 FURTHER REPORT – MCU APPLICATION FOR INDUSTRIAL BUSINESSES, SERVICE
STATION & CONVENIENCE SHOP & FOOD OUTLET (TRADIES CAFÉ) AT 139
EUMUNDI NOOSA RD & 30 LIONEL DONOVAN DV, NOOSAVILLE – MCU14/0102 &
OPERATIONAL WORKS APPLICATION FOR SIGNAGE – OPW15/0051
That Council note the report by the Development Planner to the General Committee Meeting
dated 1 June 2015 and:
A. Approve the application for a Material Change of Use (MCU14/0102) and Operational
Works (OPW15/0051) for Signage at 139 Eumundi Noosa Rd and 30 Lionel Donovan
Drive, Noosaville, subject to conditions and grounds for approval contained in the
Planning and Organisation Committee Agenda dated 26 May 2015 with amendments
to the Material Change of Use conditions 6, 8, 23, 68, 69, 84 and 91 to read as follows:
Nature and Extent of Approved Use
6. The approved Gross Floor Area of the Entertainment and Dining Business Type
1 – Café – ‘tradies café’ is 90m² 137m² and 43m² 35m² of outdoor dining. In this
regard the plans must be amended to meet this condition.
8. The Entertainment and Dining Business Type 1 – Café may operate 24 hoursis
approved as a ‘tradies café’ and must not operate outside the hours of 5am to
6pm Monday to Sunday.
Car Parking
23. A minimum of 65 67 car parking spaces and 8 motorcycle spaces must be
provided and marked on the site. The works must be undertaken in accordance
with an Operational Works approval and must include in particular:
a. provision of vandal resistant public lighting with intensities to satisfy the
requirements of Australian Standard AS1158: Public Lighting Code
b. a minimum of 3 disabled parking spaces within the total.
Operational
68. A Safety Management Plan must be developed and implemented for the
operation and maintenance of the UPSS that includes both tanks and piping. The
plan must include systems and procedures for preventing and monitoring for
spills and leaks, and the appropriate response plan to these events. The
management system must incorporate the following components:
a. objectives and targets to comply with all relevant legislation
b. hazard identification and risk assessment
c. details of the UPSS design and installation details (tank sizes, contents,
location of all relevant infrastructure)
d. list of industry standards complied with for the design, installation and
operation of the system
e. plans of the system and site
f. leak prevention measures
g. loss monitoring procedures
h. system maintenance procedures
i. emergency spillage response plan
j. loss investigation and notification procedures
Page 12 of 19