Attachment 9 - Development Approval 21675 DA
Noosa Council documents
NOOSA COUNCIL IDAS Development Application Decision Notice 4
7. To protect the environment against siltation/sediment export or soil erosion as a result of the proposed
building extensions, an erosion and sediment control plan shall be submitted in conjunction with any
Development Permit for Building Works. Site control measures such as silt fencing, controlled gravel
access to the site and controlled disposal of waste, may be necessary. Prior to commencement of
Building Works:-
7.1 all physical site control measures shall be installed and the plan adhered to, and
7.2 a $2,000 site control bond shall be lodged with Council to ensure compliance with this condition.
The $2,000 bond will be refunded less any costs incurred by Council in ensuring compliance with this
condition or any additional inspections incurred for substandard work or works undertaken not in
accordance with this permit.
Building
8. The plans submitted for a Development Permit for building works are to comply with the approved plans
9. The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and Local Law No.
12, prevents a builder or building contractor carrying out building work on a building site in a way that
makes or causes audible noise to be made from the building work:-
9.1 On a Sunday or public holiday, at any time; or
9.2 On a Saturday or a business day, before 7.00am or after 6.30pm.
A maximum penalty of $1,500 applies to an offence under this legislation.
10. We advise ‘interested parties’ i.e. ‘developer’, ‘owner’, ‘tenant’ to consider their responsibilities under the
Disabled Discrimination Act (DDA) in regard to the installation of disabled access and the provision of
disabled facilities, and that access to this building and the provision of sanitary facilities may need to
comply with the requirements of Section D Part D3 and Section F Clause F2.4 of the Building Code of
Australia.
11. An identification survey of the subject site is to be carried out by a Licensed Surveyor and is to be
submitted to Council at the time of foundation inspection or immediately thereafter. Such survey shall set
out the boundaries of the site and the position of the buildings on the site.
12. The developer must provide a suitably screened imperviously paved area large enough for all refuse and
recycling containers. A wash down area is required with a cold-water tap, hose and drain outlet
connected to sewer. The drain outlet is to be designed to prevent stormwater entry to the sewerage
system.
13. Air conditioning units shall be located in a manner which prevents noise nuisance beyond the subject land
in accordance with the nuisance provisions of the Environmental Protection Regulation 1998. On the spot
fines apply for such offences.
14. All food preparation is to be conducted within the existing approved commercial kitchen.
Land Use
15. Development undertaken in accordance with this approval must generally comply with the approved plans
of development. The approved plans are numbered SK-06, 07 issue B SK-8 & 9 Issue A dated
26/01/2000, SD1 (titled ‘Site Plan’), SD2, SD3, dated July 2005, SD4 dated May 2005 and DA-1 dated
September 2005, prepared by Andrew Hillhouse Architect and as may be amended by these conditions.
16. The open space and setback areas are to be landscaped in accordance with Council’s Policy on
Landscaping Guidelines and a properly prepared landscape plan. Such landscaping is to be completed
prior to the premises being occupied and maintained at all times thereafter.
17. Existing trees on the site and within road reserves are to be retained, except where required to be
removed due to building operations or the conduct of the approved use.
SEP o:\database\onestop\decision.doc
Print Date: 7 April 2021, 3:41 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original