Decision Notice OPW23 0147
b. Landscape works.
7. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. Traffic management during construction activities;
b. Suitable carparking arrangements for construction workers;
c. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD); and
d. provision for safe pedestrian access across the frontage of the site both during daily
construction and after daily construction has ceased.
8. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
9. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
10. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
11. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
12. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice;
b. The relevant conditions of the higher order Referral Agency Response viz.
RAP22/0019.01 to which this approval relates;
c. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines; and
d. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Works within Road Reserve/Reinstatement
13. Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out construction
works, Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
14. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
15. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Page 3 of 8
Document Set ID: 22752816
Version: 3, Version Date: 05/01/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original