Decision Notice - 010.2008.00000071.001 [As Published] · 142008.71
NOOSA COUNCIL IDAS Development Application Decision Notice 4 of 7
If any Council property or facilities should be damaged by the Applicant or any of its Consultants or
Contractors through any cause whatsoever in the course of, directly or indirectly, carrying out the
engineering works, the Applicant and/or its Contractors shall forthwith notify the Manager Land
Development and shall forthwith rectify the damage to that property or facility at its cost and to the
satisfaction of the Manager Land Development.
All rectification works are to be completed prior to the commencement of the use or, alternatively, the
Applicant may request the Council to carry out the rectification work at the Applicant’s cost, such cost
being paid by the Applicant to the Council prior to the commencement of the use.
In the case of any emergency the Council shall be entitled to rectify such damage at the cost of the
Applicant, such cost being paid prior to the commencement of the use.
11. The development of the site shall be carried out in such a manner as to prevent dust and/or sand
nuisance to residents and/or tenants in the vicinity of the development.
12. Construction work and other associated activities are permitted only during the hours of 7.00 am and 6.00
pm Monday to Saturday. No work is permitted on Sundays or public holidays, except where extended
hours are approved by the Manager-Land Development or his nominee.
13. All signage, including that for safety during construction shall be in accordance with the Manual of Uniform
Traffic Control Devices and Traffic Infrastructure (Roads) Act.
14. Safe pedestrian access on Grosvenor Terrace shall be maintained at all times. Should footpath / road
closures be necessary to carry out construction works, Council’s Construction Technical Officer (ph 0410
512 505) must be notified prior to the proposed closure.
15. Sediment and erosion control measures must be in place prior to works commencing. If such measures
are not in place or are not satisfactory, “on the spot “fines may be issued. Such fines can be issued if
sediments from the site are found to enter or have the potential to enter Council’s stormwater system or
natural waterways. Council’s Manager – Land Development may request further controls to be installed
should approved measures be inefficient.
16. These works are also to be in compliance with the relevant conditions of Development Permit No. 23116
DA.
17. Pursuant to Section 3.5.21(5) of the Integrated Planning Act 1997, the Relevant Period is two (2) years
from the day this permit takes effect (30 January 2010) during which time all conditions must have been
complied with and the Plan of Survey lodged with the Council for endorsement.
18. Notwithstanding that Council has checked the plans with due care, where it is found during construction
that variations from Council's standards exist, then Council standards shall apply.
NSC c:\docume~1\amoore\locals~1\temp\bcl technologies\easypdf 5\@bcl@740560f5\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2008.00000071.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 29 KB (small file)
- File type
No other editions are linked here.