Attachment 2
NOOSA COUNCIL
Capital Works 38,026,535 br tt Bvt 2,858,287 353,000 bl 0-3] RI)
Noosaville Alec Loveday Park Pedestrian Bridge Renewal SEQCSP 18,968 Planning, design and approvals underway. Expected construction
completion Q2.
Tewantin Doonella Bridge Renewal BRP 500,000 187,298 Multi-year project. Works options assessment currently underway.
Kin Kin Wahpunga Lane Bridge Renewal Annual BRP 556,556 200,000 Multi-year project. Construction phase currently underway.
Cooroy Belli Creek Road Bridge Renewal BRP 1,177,816 (19,978) Multi-year project. Construction phase currently underway.
Noosa Heads Garth Prowd Brdge Renewal BRP 3,020,000 334,788 Multi-year project. Procurement tender phase currently underway.
Black Mountain Lawnville Road Bridge Renewal BRP 291,922 (1,719) Multi-year project. Design phase awaiting outcomes of grant
Cooroy Gumtree Drive Pedestrian Bridge Construction 95,000 2,864 Environmental approvals com plete. Design and construct to occur
Total Bridges 5,084,738 1,078,777 200,000 0
Noosaville Noosa Waters Lock & Weir Annual Renewal Program 1,180,000 38,457 Multi-year project. Procurement tender phase currently underway.
Renewal of revetment wall at O-Boats Gympie Tce, Noosaville 50,000 1,311 Scope of works deferred to align with Gympie Tce Masterplan worksin
Noosa Heads Dog Beach SEMP 1,041,000 3,927 ~ project. Procurement tender phase currently underway.
Worksto occur in Q1-Q2
Noosa Waters Revetment Wall 43,247 Multi-year project. Procurement tender phase currently underway.
Noosa Heads Main Beach Sand Recycling System Pipe Renewal 50,000 100,000 Works delayed to align with season demand for sand pumping system.
Works commencing Q1.
Noosa Main Beach Removable Sand Break Seating Structure 70,266 Planning and design complete. Worksto be undertaken Q1-Q2
Noosa Main Beach Shower & Rock Wall Seating SEQCSP 30,061 28,629 Construction underway. Variation for plumbing and drainage site
considerations.
Sunshine Beach - Beach Access Renewals SEQCSP 250,000 (338) Multi-year project. Some minor upfront costs incurred in 2021/22 to
reduce 2022/23 budget.
Noosa Main Beach Western end rock wall 87,000 Variation to address additional western end rock wall intervention works occurring
in conjunction with existing underway shower and rock wall works
Total Coastal Canals and Waterways 2,571,000 286,931 115,629 0
Cooroy Cemetery Plant & Equipment Shed 136,656 Planning approvals underway. Worksto be undertaken Q1-Q2
Total Cemeteries 0 136,656 0 0
Sunrise Beach Shopping Centre Emergent Works (6,194) 200,000 Emergent works required to facilitate new anchor tenant
Sunrise Beach Shopping Complex - Roof Renewal 260,000
Total Commercial Land & Property 260,000 (5,194) 0 200,000
Rufous St - Stage 3 Community House, Car Park & Landscape BBRF 722,557 Multi-year project. New Community House construction complete.
Refit of old community house for Digital Hub in tender phase.
NAC Replacement of Light Pole Fittings 59,500 Procurement tender phase underway. Worksto be undertaken Q1-Q2
Living Fire Tech Lab - Disaster Recovery QRA 1,484,908 175,952 Multi-year project. Gurrently in procurement tender phase. Worksto
be undertaken 2022/23
Peregian Beach Rufous St Public Art QRA 49,864 Worksto be undertaken during 2022/23
Page 42 of 122See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.