GENERAL COMMITTEE MEETING AGENDA 15 AUGUST 2022
Page 91 of 122
GENERAL COMMITTEE MEETING AGENDA 15 AUGUST 2022
Corporate Plan Key Operational Initiatives Outcomes Responsible Update Status Q3 Q4
Focus Areas Areas/Officers
4.8 Undertake long | Bridge Renewal Program Replacement and upgrading | Infrastructure | Cooran Tablelands Rd bridge renewal reached | Behind Behind
term financial of bridges to improve the Planning, practical completion 27 January 2022. Schedule | Schedule
sustainability road network and to deliver Design & Kin Kin Wahpunga Lane hinterland bridge
Planning eecueinle Penge ee Deen construction contractor impacted by February
Nee eee ane : INP RNEG AESEL eniageMneUt he Noe 2022 floods with the loss of machinery; as a
mbetere Deis Se contract completion re-forecast to August
Delivery ‘
Manager Cooroy Belli Creek Road, hinterland bridge
design is completed and tender evaluation
completed; contract awarded May22, construction
forecast July 2022 to September 2022. Funding
variation submission to BRP in April 2022; no
update from Federal Govt this report period.
Lawnville Rd hinterland bridge design is
completed. BRP funding variation submitted for
withdrawal of round 5, and application submitted
at round 6; no update from Federal Govt this
report period.
Tewantin Lake Doonella bridge is undergoing
options analysis for remediation and final report
due late July 2022. Reference design ITQ in
development.
Garth Prowd bridge completed options
assessment for remediation and pathway
widening. Tender under evaluation July2022.
Shire pedestrian bridges, Cooroy Gumtree Drive
pedestrian bridge environmental approvals and
design IFC completed; council bridge crew will
deliver works in 22/23 FY. Alec Loveday
pedestrian bridge is in final scope assessment
stage and pending environmental approvals;
works also will be completed in 22/23 FY.
Page 91 of 122See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.