MCU10/2083 Development Application part 2 - Attachment 7 - Stormwater Management Plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn
5.4 STORMWATERQUALITYTREATMENTTRAIN
AWSUDtreatmenttrainhasbeendevelopedtomeetthereductioncriteriaestablishedinTable10.BioRetention
areas with a total surface / treatment area of 113m2 will be utilised to capture and treat overland flows from
perviousandimperviousareas.HealthyWaterways‘WSUDTechnicalGuidelines’,statesthattoachieveadequate
loadreductiontargets,bioretentionsystemsaretobesizedatapproximately12%ofthecatchmentarea.Table
11providesacatchmentbreakdownforthetotalBioRetentionarea.
Table11BioRetentionSystemDetails
BioretentionArea PercentageofCatchment
CatchmentArea(ha) 2
(m ) Area(%)
0.386 113 2.93
ThebioretentionfiltermediashouldbeplantedwithaselectionofthevegetatedtypesasoutlinedinTable12.
Table12–SuitableBioRetentionVegetationTypes
Planting
Height
ScientificName CommonName Form Density
(mm)
(Qty/m2)
Myoporumparvifolium CreepingBoobialla Prostrate 150 46
Cymbopogonrefractus BarbedWireGrass Tufted 300 810
Dianellacaeruleacv‘LittleJess’ BlueFlaxlily Tufted 400 46
Dichelachnecrinita LongHairedPlumeGrass Tufted 200 68
Erograstiselongatacv‘Elvera’ Elvera Tufted 300 68
Imperatacylindrica BladyGrass Tufted 500 46
Lepidospermalaterale VariableSwordSedge Tufted 750 810
Lomandraconfertifoliasubsp MattingLomandra Tufted 300 46
confertifolia
Lomandraconfertifoliasubsp MatRush Tufted 400 46
pallida
Poalabillardierecv‘Eskdale’ Eskdale Tufted 450 68
Themedaaustralis KangarooGrass Tufted 400 68
Themedaaustraliscv‘Mingo’ Mingo Tufted 200 810
The plants selected must be able to tolerate periods of inundation and a saturated filter material. Therefore
plants with extensive fibrous root systems are required. Refer to Australian Runoff Quality and BCC WSUD
EngineeringGuidelinesTable12.1foradditionalinformationandsuitableplantvarieties.
5.5 MAINTENANCE
AbioretentionbasinmaintenanceplanwillbeprovidedattheOperationalWorksStage.
SITEBASEDSTORMWATERMANAGEMENTPLAN–RevisionD 37GibsonRoad,Noosaville Page 11
[OCR of page images]
JF
AU
URBANCONSULTANTS
5.4 STORMWATER QUALITY TREATMENT TRAIN
A WSUD treatment train has been developed to meet the reduction criteria established in Table 10. Bio-Retention
areas with a total surface / treatment area of 113m* will be utilised to capture and treat overland flows from
pervious and impervious areas. Healthy Waterways ‘WSUD Technical Guidelines’, states that to achieve adequate
load reduction targets, bio-retention systems are to be sized at approximately 1-2% of the catchment area. Table
11 provides a catchment breakdown for the total Bio-Retention area.
Table 11 - Bio-Retention System Details
Bio-retention Area Percentage of Catchment
(m?) Area (%)
0.386 113 2.93
Catchment Area (ha)
The bio-retention filter media should be planted with a selection of the vegetated types as outlined in Table 12.
Table 12 — Suitable Bio-Retention Vegetation Types
. Planting
ee Height .
Scientific Name Common Name Form nan Density
(Qty/m’)
Myoporum parvifolium Creeping Boobialla Prostrate | 150 4-6
Cymbopogon refractus Barbed Wire Grass Tufted 300 8-10
Dianella caerulea cv ‘Little Jess’ Blue Flax-lily Tufted 400 4-6
Dichelachne crinita Long Haired Plume Grass Tufted 200 6-8
Erograstis elongata cv ‘Elvera’ Elvera Tufted 300 6-8
Imperata cylindrica Blady Grass Tufted 500 4-6
Lepidosperma laterale Variable Sword Sedge Tufted 750 8-10
Lomandra confertifolia subsp Matting Lomandra Tufted 300 4-6
confertifolia
Lomandra confertifolia subsp Mat Rush Tufted 400 4-6
pallida
Poa labillardiere cv ‘Eskdale’ Eskdale Tufted 450 6-8
Themeda australis Kangaroo Grass Tufted 400 6-8
Themeda australis cv ‘Mingo’ Mingo Tufted 200 8-10
The plants selected must be able to tolerate periods of inundation and a saturated filter material. Therefore
plants with extensive fibrous root systems are required. Refer to Australian Runoff Quality and BCC WSUD
Engineering Guidelines Table 12.1 for additional information and suitable plant varieties.
5.5 MAINTENANCE
A bio-retention basin maintenance plan will be provided at the Operational Works Stage.
SITE BASED STORMWATER MANAGEMENT PLAN — Revision D 37 Gibson Road, Noosaville 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.