Other Change Decision Notice - Council Meeting Decision 132007 2446 05 · 132007.2446.05
the sewer main and be equivalent in width to twice the depth to invert level of the sewer
at the deepest point within the allotment (measured from the finished surface) and be
no less than 3.0m wide overall. In this regard a licensed surveyor shall accurately locate
all sewer mains and determine the necessary width of the easement, which shall be
shown on any plans submitted for Operational Works / Building Works approval. To this
extent the surveyor shall certify that the sewer and the zone of influence is wholly
contained within the easement to be created.
In addition to this the Applicant’s Solicitor shall give Council’s Solicitor an appropriate
undertaking in writing that the Title Deed and the easement documents will be lodged at
the Land Titles Office and any additional Titles Office forms or requisitions requiring the
consent of Council will be attended to promptly.
A duly executed copy of the easement shall be submitted to Council for perusal prior to
the use commencing. Any changes required by Council’s Solicitor must be corrected
immediately.
33. No building or other structure shall be constructed or encroach over an easement.
Town Water Supply
34. The site shall be connected to Council’s existing town water supply and be constructed
in accordance with Council’s standards and requirements at no cost to Council.
35. Each individual water connection to the water reticulation system shall extend to the
property boundary and be metered. All fees for the supply of water meters shall be paid
to the Council.
36. All water meters must be located outside the property boundary and in an easily
assessable location to facilitate unhindered reading by Council and/or Council’s
contracted water meter readers, and not behind fences or locked gates. In this regard
approval of the water meter configuration and location must be obtained from Council’s
Water & Sewerage Capital Works Manager prior to lodgement and approval of hydraulic
drawings.
Earthworks
37. Any filling works required on site shall be carried out in accordance with Council’s
Planning Scheme Policy PSP5 – Engineering Design Standards, so as not to cause the
additional ponding of water on any adjoining lands or the blockage of, or interference
with, any natural stormwater runoff.
38. Earthworks carried out on site shall not affect the structural integrity of any of the existing
fences or structures that border the development site. Fences that are affected shall be
replaced prior to the Building Certifier issuing the Certificate of Classification. In this
regard any fences to be replaced shall be clearly shown on the plans submitted for
Operational Works approval.
Erosion and Sediment Control
39. Any person acting on this permit shall prevent erosion and sediment export from leaving
the site. Site control measures such as silt fencing, controlled gravel access to the site
and controlled disposal of waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are
required to be submitted to the Council for approval prior to obtaining a Development
Permit for Operational Works.
Vehicle Access and Car Parking
40. A vehicular access driveway and carparking on the site shall be constructed generally
in accordance with plan titled Site-Parking numbered P1 Sheet S2 issue C dated
16/04/09 and as amended by Council in red. A Development Permit for Operational
Works shall be required.
Page 6 of 24
Document Set ID: 24061481
Version: 7, Version Date: 28/08/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Other Change Decision Notice - Council Meeting Decision 132007 2446 05.pdfRelated documentApplication case desk ↗
About this file
- File size
- 254 KB (small file)
- File type
No other editions are linked here.