2016008949 DECISION NOTICE - Signed

Attached to the e-mail Operational Works Application OPW16/0338.

of 16
                                                                                                                                     Head Office:
                                                                                                                     Ground Floor, 33 King Street
                                                                                                                            Caboolture QLD 4510
                                                                                                                                Mailing Address:
                                                                                                                PO Box 953, Caboolture QLD 4510
                                                                                                                    1300 0 UNITY (1300 086 489)
                                                                                                                           www.unitywater.com
                                                                                                                                    ABN: 89 791 717 472




                                                     DECISION NOTICE
                 South-East Queensland Water (Distribution and Retail Restructuring) Act 2009


                                                            Application Details

      Connection Application No:                 2016008949

      Street Address:                            10 Pelican St, 5 & 13 Memorial Ave TEWANTIN, QLD 4565

      Property Description:                      Lot 1 RP73080 & Lot 10 SP236319
      Local Government Area:                     Noosa Shire Council


                                                              Decision Details

      Decision:                                            Approval

      Decision Date:                                       18/11/2016

      Assessment Officer:                                  Mike Laverty

      Category of Connection:                              Other

      Approval Phase:                                      Connection Approval & Network Works Approval

      Approval Type                                        Alteration to Unitywater Network

      Description:                                         Proposed Commercial Development - Extension of existing
                                                           RSL building and Sewermain Re-alignment with Build-over
                                                           Sewer aspect and Water Supply/Fire Service.

      Advice:                                              Refer to condition CAS 12 regarding the Building over and/or
                                                           adjacent to Unitywater asset component of this Connection
                                                           Application




                                                                                                                                            Page 1 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                            Unitywater has certification to
                                                                                                                 OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                             Environmental ISO 14001:2004 Reg No 4259
                                                                                                                 Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015             Next Review Date:19/02/2018

Log in to download the original (2016008949 DECISION NOTICE - Signed.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 15 pages

Page 2

                                                                Conditions

  General Conditions
  This approval authorises the connection of network infrastructure and/or property services infrastructure at
  Lot 1 RP73080 & Lot 10 SP236319 to Unitywater’s infrastructure subject to the following conditions.


  General Condition                                                                                                    Timing

  GEN
            When approval lapses
   1
            Ensure the water connection aspects of this water approval are carried out                                 At all times.
            within 4 years of the date of this water approval taking effect.


  Connections Approvals General Conditions                                                                             Timing

  CAG
            Approved demand
   2
            Do not exceed the following approved additional demand for the                                             To be
            development:                                                                                               maintained at all
            Water Supply: 9.2 equivalent persons, water                                                                times.
            (Based on 683m2 [email protected] equivalent persons water / 100m2 GFA)
            Sewerage: 10.6 equivalent persons, sewerage
            (Based on 683m2 [email protected] equivalent persons sewer / 100m2 GFA)
            Where the equivalent person rate is determined in accordance with
            Unitywater’s Schedule of Works.
  CAG
            Damage to existing services and assets
   3
            Notify Unitywater about any damage caused to existing water supply                                         At all times
            and/or sewerage services and assets above or below the ground and                                          during
            repair any damage to the service or asset to the same standard or better                                   construction and
            as existed before the damage occurred. Notification to Unitywater and                                      until works are
            repairs are to be done as soon as reasonably possible.                                                     accepted ‘Off-
            Any repair work proposing to alter or affect the alignment or level of                                     Maintenance’.
            existing water supply and/or sewerage services and assets must first be
            referred to Unitywater for approval.
  CAG
            Existing services alterations/relocations - cost
   4
            Carry out any change to Unitywater’s existing infrastructure authorised by                                 At all times
            this approval at no cost to Unitywater.                                                                    during
                                                                                                                       construction and
                                                                                                                       until works are
                                                                                                                       accepted ‘Off-
                                                                                                                       Maintenance’.




                                                                                                                                           Page 2 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Page 3

  Connections Approvals Water                                                                                          Timing

  CAW
              Reticulated water supply
   1
                   a) Provide reticulated water supply to the development, including a                                 a) Prior to the
                      metered water service line and connection(s) to Unitywater’s                                         issue of the
                      existing water supply network in accordance with Unitywater’s                                        Certificate of
                      Connections Administration Manual & South East Queensland                                            Completion.
                      Water Supply and Sewerage Design and Construction Code.
                      This condition is imposed under section 99BRDJ – conditions                                      b) Prior to the
                      about non-trunk infrastructure of the South-East Queensland                                          commencem
                      Water (Distribution and Retail Restructuring) Act 2009.                                              ent of the
                   b) Engineering drawings and specifications detailing the works                                          works.
                      required by this approval must be in accordance with Unitywater’s
                      South East Queensland Water Supply and Sewerage Design and                                       c) Prior to the
                      Construction Code.                                                                                   issue of the
                   c) As-constructed drawings and data which detail the works                                              Certificate of
                      constructed by the Applicant must be compiled and submitted in                                       Completion.
                      accordance with Unitywater’s South East Queensland Water
                      Supply and Sewerage Design and Construction Code.                                                d) At the time
                   d) The developer must pay all costs associated with the connection,                                     the works are
                      inspection and acceptance of the proposed works.                                                     carried out.


  Connections Approvals Sewer (CAS)                                                                                    Timing

  CAS
            Sewer reticulation
   1
                 a) Provide reticulated sewerage to all lots within the development,
                    including a property connection to each lot and connection(s) to                                   a) Prior to the
                    Unitywater’s existing sewerage network in accordance with                                              issue of the
                    Unitywater’s Connections Administration Manual & South East                                            Certificate of
                    Queensland Water Supply and Sewerage Design and Construction                                           Completion
                    Code.
                    This condition is imposed under section 99BRDJ – conditions                                        b) Prior to the
                    about non-trunk infrastructure of the South-East Queensland Water                                      commencem
                    (Distribution and Retail Restructuring) Act 2009.                                                      ent of the
                 b) Engineering drawings and specifications detailing the works                                            works
                    required by this approval must be in accordance with Unitywater’s
                    South East Queensland Water Supply and Sewerage Design and                                         c) Prior to the
                    Construction Code.                                                                                     issue of the
                 c) As-constructed drawings and data which detail the works                                                Certificate of
                    constructed by the Applicant must be compiled and submitted in                                         Completion
                    accordance with Unitywater’s South East Queensland Water
                    Supply and Sewerage Design and Construction Code.                                                  d) At the time
                 d) The developer must pay all costs associated with the connection,                                       the works are
                    inspection and acceptance of the proposed works.                                                       carried out
  CAS
            Sewer service connection points
   2
            Provide service connection points to all lots within the development. This                                 Prior to the
            condition is imposed under section 99BRDJ of the South-East Queensland                                     issue of the
            Water (Distribution and Retail Restructuring) Act 2009.                                                    Certificate of
            Advice: The Applicant may request Unitywater to undertake these works                                      Completion.
                                                                                                                                           Page 3 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Page 4

            at the Applicant’s cost.
  CAS
            Construct sewerage main
   4
            Provide sewerage to the upstream property/stage boundary/s to enable                                        Prior to the
            future mains extensions. This condition is imposed under section 99BRDJ                                     issue of the
            – conditions about non-trunk infrastructure of the South-East Queensland                                    Certificate of
            Water (Distribution and Retail Restructuring) Act 2009.                                                     Completion
            Note: Upstream property is any adjoining catchment identified as requiring
            to be serviced by the proposed sewerage infrastructure regardless of the
            contour topography
  CAS
            Relocate/Re-align sewer main
   7
            Relocate/re-align the existing 150mm diameter sewer main from (MH EX/1                                      Prior to
            to MH 3/1). This condition is imposed under section 99BRDJ – conditions                                     connection to
            about non-trunk infrastructure of the South-East Queensland Water                                           the Unitywater
            (Distribution and Retail Restructuring) Act 2009.                                                           network.

  CAS       Easements
   9
            Easements must be provided over sewerage mains traversing the site in
            accordance with Unitywater’s South East Queensland Water Supply and                                         Prior to the
            Sewerage Design and Construction Code.                                                                      issue of the
                                                                                                                        Certificate of
            Note: Easement terms will be the most current registered dealing held by
                                                                                                                        Completion
            the Department of Natural Resources & Mines and will not be altered or
            amended.
  CAS       Building over and/or adjacent to Unitywater asset – Approval attached
   12
            Your development has a requirement that the property owner obtain
            ‘Building Over and/or Adjacent to Unitywater Asset’ (BOAA) consent for                                      Prior to the
            building structures proposed to be built within proximity of the re-aligned                                 commencement
            150mm sewer main traversing the site .                                                                      of any works for
                                                                                                                        that building or
            This BOAA approval has been granted and the approval document is
                                                                                                                        structure.
            attached at the end of this decision notice.



  Network Works Approval Conditions                                                                                     Timing

  NWA
              Approved Network Works Drawings
   1
              Construct the network works generally in accordance with the approved                                     At all times
              design drawings as follows:                                                                               during
                                                                                                                        construction and
                Unitywater Approved Network Works Drawings                                                              until Network
                 Drawing                                                                                                Works are
                                                 Title                       Prepared by                 Date           accepted ‘Off-
                 Number
                                                                                                                        Maintenance’.
                   C002                                                      VT Consulting
                                  Sewer Reticulation Notes                                            14/11/16
                   Rev B                                                      Engineers
                   C003           Sewer Reticulation Layout                  VT Consulting
                                                                                                      15/11/16
                   Rev D          Plan                                        Engineers



                                                                                                                                            Page 4 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                            Unitywater has certification to
                                                                                                                 OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                             Environmental ISO 14001:2004 Reg No 4259
                                                                                                                 Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015             Next Review Date:19/02/2018

Page 5

                   C004           Sewer Reticulation Long                    VT Consulting
                                                                                                      14/11/16
                   Rev C          Section                                     Engineers
                   C005           Sewer Reticulation Build                   VT Consulting
                                                                                                      14/11/16
                   Rev B          Over Sewer Sections                         Engineers
                1620/HWD/         Hydraulic Services Basement
                   H05            Floor Plan (1 of 2) / Water &            BRW Enterprises            20/10/16
                 Rev DD1          Fire Services
              This condition is imposed under section 99BRDJ – conditions about non-
              trunk infrastructure of the South-East Queensland Water (Distribution and
              Retail Restructuring) Act 2009.
  NWA
              Pre-start Meeting
   3
              Construction of the water supply and sewerage works must not                                              Prior to the
              commence until a joint Pre-start Meeting has occurred, between:                                           commencement
                 (a) the responsible consulting engineer;                                                               of construction.
                 (b) the principal contractor and the subcontractor (if any); and
                 (c) a Unitywater development officer.
  NWA
              Works at Applicant’s expense
   4
              The Applicant is responsible for all costs associated with the works that                                 At all times
              need to be constructed to comply with conditions unless otherwise stated                                  during
              in the condition.                                                                                         construction and
                                                                                                                        until works are
                                                                                                                        accepted ‘Off-
                                                                                                                        Maintenance’.
  NWA
              Standards
   5
                                                                                                                        At all times
              Construct all works in accordance with the approved drawings, the South                                   during
              East Queensland Water Supply and Sewerage Design and Construction                                         construction and
              Code, Unitywater’s Connections Administration Manual, other conditions                                    until works are
              stated in this Decision Notice for a water approval.                                                      accepted ‘Off-
                                                                                                                        Maintenance’.
  NWA
              Council approval
   6
              Submit a copy of the Council development permit that is consistent with
              the connection approval with the request for the Pre-start Meeting.
                                                                                                                        Prior to request
              Note: If a copy of the Council development permit is not able to be                                       for a Pre-start
              provided, a written statement describing the reasons why the approval is                                  Meeting.
              not attached must be submitted with the pre-start request form.
  NWA
              Workplace health and safety
   7
              Comply with the Work Health and Safety Act and Regulations.
              Note: Should the Applicant fail to appoint a Principal Contractor within                                  At all times
              the meaning of that Act within the time required, the Applicant shall be                                  during
              the Principal Contractor under that Act and shall perform all duties of the                               construction and
              Principal Contractor including but not limited to:                                                        until works are
                                                                                                                        accepted ‘Off-
                       Giving notice to the Director of Accident Prevention prior to                                   Maintenance’.
                        commencing notifiable work; and

                                                                                                                                            Page 5 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                            Unitywater has certification to
                                                                                                                 OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                             Environmental ISO 14001:2004 Reg No 4259
                                                                                                                 Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015             Next Review Date:19/02/2018

Page 6

                       Payment of the relevant fees under the Act.



  Connections Approvals Advice (CAA)

  CAA
            Infrastructure charges
   1
            Payment of Levied Charges is required in accordance with Unitywater’s Infrastructure Charges
            for water supply and sewerage. Unitywater may give the Applicant an Infrastructure Charges
            Notice within 10 business days after the giving of this Decision Notice.
            From 1 July 2014, all Infrastructure Charges for water supply and sewerage infrastructure
            networks controlled by Unitywater, regardless of when the Infrastructure Charges Notice was
            issued, shall be paid directly to Unitywater.
  CAA
            Works in roads
   3
            Where works associated with the Connection Application results in works to be carried out in
            a publicly controlled place e.g. roads, it is the Applicant’s responsibility to gain the necessary
            approvals from the relevant authority e.g. council, Department of Transport and Main Roads.
            It is the Applicant’s responsibility to ensure that it has all necessary consents and approvals to
            carry out any works in a publicly controlled place prior to starting any such works.
            The approval for works in roads must be attached to the Request for Pre-start Meeting form.
  CAA
            State Assessment and Referral Agency (SARA)
   4
            This approval relates to Connection Application requiring approval under the South-East
            Queensland Water (Distribution and Retail Restructuring) Act 2009 only. It is the Applicant’s
            responsibility to ensure any works requiring approval/s under the Sustainable Planning Act
            2009 (Qld) are obtained from State Assessment and Referral Agency (SARA) prior to the
            request for a Pre-start Meeting.
  CAA
            The Aboriginal Cultural Heritage Act 2003
   6
            The Aboriginal Cultural Heritage Act 2003 commenced in Queensland on April 16, 2004. The
            Aboriginal Cultural Heritage Act 2003 establishes a Duty of Care for indigenous cultural
            heritage. This applies on all land and water, including freehold land. The Cultural Heritage
            Duty of Care lies with the person or entity conducting the activity.
            Penalty provisions apply for failing to fulfil the Cultural Heritage Duty of Care.
            Unitywater strongly advises the Applicant to contact the Cultural Heritage Co-ordination Unit
            on 07 32476212 to discuss any obligations under the Aboriginal Cultural Heritage Act 2003.
  CAA
            Level of service
   7
            The Water and Sewerage Services Code for Small Customers in South East Queensland and
            the Unitywater’s Customer Service Standard specify the level of service for Unitywater’s water
            and sewerage services.
  CAA
            Other services
   8
            It is the Applicant’s responsibility to acquire the necessary approvals from the relevant
            authority or service provider to alter or relocate their service.




                                                                                                                                           Page 6 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Page 7

  CAA
            Other approval requirements and compliance with all laws
   9
            This approval only authorises the connection to Unitywater’s infrastructure. This approval
            does not remove the need for other approvals in order to carry out the necessary work for the
            development.
            For example, the Applicant should consider the need to comply with relevant standards and
            obtain approvals for impacts arising from sediment and erosion control, flora and fauna and
            traffic/roads, including traffic management etc.
            The Applicant is responsible for obtaining all necessary approvals for its development and
            complying with all laws including all environmental laws.
  CAA
            Third party property
   10
            If any infrastructure authorised by this approval is to be constructed on property that is not
            owned or controlled by the Applicant, it is the Applicant’s or developer’s responsibility to gain
            the necessary consents to install that infrastructure.
  CAA
            Connection to Unitywater network/s
   11
            Connections to the existing Unitywater water supply and/or sewerage network/s will only be
            carried out by Unitywater or as agreed with Unitywater’s Private Works section and by
            application. Connections will only be completed after the new infrastructure has been
            accepted ‘On-Maintenance’.
            Works on or in close proximity to existing Unitywater infrastructure require consultation with
            Unitywater Private Works prior to commencement of construction. Private Works shall be
            contacted (allow a minimum of five working days for processing) prior to commencing work.
            The requirement for a Network Intervention application will require additional processing time.
  CAA
            Water service/s installation
   12
            If this application is subject to the payment of Infrastructure Charges, Unitywater will install
            the water service/s within 20 business days after the payment of the Infrastructure Charges.
  CAA
            Errors and Omissions
   13
            This approval shall not be taken to mean that the drawings have been checked in detail,
            Unitywater accepts no responsibility whatsoever for the survey information, the design, or for
            the accuracy of any information or detail contained in the drawings and specifications.
            Where errors or omissions occur in the design drawings or specifications, or where works do
            not conform to or meet Unitywater standards, the Applicant’s Consultant shall rectify such to
            comply with those standards at no cost to Unitywater.
            Where drawings contain insufficient detail or do not contain details of works that are either
            necessary or associated with the development then these works shall be designed and
            constructed to Unitywater standards, as required by Unitywater.
            Unitywater reserves the right to amend the approved drawings or request further information
            should this become necessary. Only the Unitywater approved drawings shall be used for
            construction.
  CAA
            Existing water meter/s
   14
            The Applicant is advised that if the existing water meter currently serving the property will no
            longer be required, an application (Standard Connection Request) must be made to
            Unitywater to disconnect the meter.
            A fee is applicable for the disconnection of services.
                                                                                                                                           Page 7 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Page 8

            Refer to Unitywater Fees and Charges schedule at: www.unitywater.com/fees-and-charges.

  CAA
            Private Works
   15
            The Applicant is advised that all connection works by Unitywater Private Works are quoted on
            application.
            This requires the applicant to submit a completed Water Supply and Sewerage Services
            Private Works Application form to the email address on the form together with this water
            approval to enable a quotation to be produced by Private Works.
            The form is available at: www.unitywater.com.au/private-works .


                                                Internal Review and Appeal Rights

  You have a right to apply for an internal review of the decision including the conditions attached to this
  decision. Under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009 an
  appeal against a decision must be, in the first instance, by way of an application for internal review.

  The attached information sheet provides information about the internal review and appeal processes,
  including how to apply and the details of the information required to be submitted with your application.

  Please note that any application for an internal review of this decision must be made within 30 business
  days after the date the application was decided (see Decision Details on Page 1).

  It is advised that prior to the submission of a formal application for internal review, the applicant should
  contact the responsible Unitywater officer to discuss the issues of concern. This can be done by
  emailing [email protected] and it needs to be made clear in the email content that
  this initial enquiry is not a formal application for internal review, but instead is a preliminary enquiry to
  discuss issues that have been conditioned in the Unitywater Decision Notice and/or Infrastructure
  Charges Notice. The Unitywater officer and Development Services may consider changes to the
  Decision Notice and/or Infrastructure Charges Notice without the need of an Internal Review. This
  preliminary enquiry and consultation does not have an effect on the 30 business days of the ‘decision
  period’ and if the issue cannot be resolved within this time, the only recourse of Internal Review is as
  explained in the process above.


                                                               Advisory Notes

  The following notes are included for guidance and information only and do not form part of the
  conditions of this approval.

  Development Approval

  This approval does not authorise development other than the connection approval. It is the applicant’s
  responsibility to obtain any necessary development approvals for development related to this
  connection approval.

  Infrastructure Charges
  This approval may trigger an Infrastructure Charges Notice to be issued in accordance with Unitywater’s
  Infrastructure Charges Schedule adopted under the South-East Queensland Water (Distribution and
  Retail Restructuring) Act 2009. If a charge is applicable, a separate Infrastructure Charges Notice will be
  given.



                                                                                                                                           Page 8 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Page 9

  Aboriginal Cultural Heritage Act 2003

  There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals
  pursuant to the Aboriginal Cultural Heritage Act 2003.

  The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out
  an activity must take all reasonable and practicable measures to ensure the activity does not harm
  Aboriginal cultural heritage.” It is an offence to fail to comply with the duty of care. Substantial monetary
  penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be
  issued by the Land Court, and the Minister administering the Act can also issue stop orders for an
  activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of
  Aboriginal cultural heritage.

  You should contact the Cultural Heritage Unit on 07 32476212 to discuss any obligations under the
  ACH Act.

  Yours sincerely




  Jarrod Murphy
  Principal Development Engineer
  Development Services




                                                                                                                                           Page 9 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Page 10

              INFORMATION SHEET – REVIEWS AND APPEAL PROCESS

              Division 1 Preliminary

              99BRAW Meaning of interested person and original decision
              (1) An interested person for this part is an applicant under this chapter who—
              (a) has been given a decision notice; or
              (b) if the period during which the application was required to be decided under the
              relevant connections policy has expired—has not been given a decision notice; or
              (c) has had 1 or more of the following charges levied for a connection, other than for a
              standard connection—
              (i) a connection charge;
              (ii) a property service works charge;
              (iii) a charge under an infrastructure charges notice; or
              (d) has been given a notice under section 99BRDG about a conversion application, or
              there is a deemed refusal for the application.

              (2) Each of the following is an original decision—
              (a) the decision or action for which a decision notice was given (an approval decision);
              (b) if the period during which an application was required to be decided under the
              connections policy has expired—the failure to give a decision notice for the application (a
              failure to decide);
              (c) the decision to levy a charge for a connection mentioned in subsection (1)(c)(i) or (ii) (a
              charge decision);
              (d) the decision to give an infrastructure charges notice;
              (e) the refusal or deemed refusal of a conversion application (a conversion decision).

              (3) However, for an original decision under subsection (2)(a), an interested person cannot
              appeal a water approval condition that became a condition under section 99BRAM.

              99BRAX Other definitions for pt 4 In this part—
              charge decision see section 99BRAW(2)(c).
              conversion decision see section 99BRAW(2)(e).
              deemed refusal, for a conversion application, means a refusal of the application that is
              taken to have happened if a decision is not made within the required period for the
              application.
              required period, for a conversion application, see section 99BRDF(6).
              standard appeal period, for an appeal under division 3 or 4, means—
              (a) if the notice for the review decision is given to the interested person—within 20
              business days after the notice was given; and
              (b) otherwise—within 20 business days after the review decision is taken to have been
              made under section 99BRBC(4).

              Division 2 Internal reviews

              99BRAY Appeal process starts with internal review
              An appeal of an original decision, other than an appeal against a compliance notice, must
              be, in the first instance, by way of an application for internal review.

              99BRAZ Who may apply for review
              (1) An interested person for an original decision may apply for an internal review of the
              decision (an internal review application).
              (2) An internal review application may be made only to the chief executive officer of the
              relevant distributor-retailer (the reviewer).

                                                                                                                                          Page 10 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Page 11

              99BRBA Requirements for making internal review application
              An internal review application must be—
              (a) accompanied by a statement of the grounds on which the applicant seeks the review of
              the decision; and
              (b) supported by enough information to enable the reviewer to decide the application; and
              (c) made within 30 business days after the day—
              (i) for a failure to decide or a deemed refusal of a conversion application—the relevant
              decision was required to be made; or
              (ii) otherwise—the original decision is made.

              99BRBB Review decision
              (1) The reviewer must, within the review decision period—
              (a) review the original decision the subject of the application; and
              (b) make a decision (the review decision) to—
              (i) confirm the original decision; or
              (ii) amend the original decision; or
              (iii) substitute another decision for the original decision.
              (2) The application must not be dealt with by—
              (a) the person who made the original decision; or
              (b) a person in a less senior office than the person who made the original decision.

              (3) Subsection (2)—
              (a) applies despite the Acts Interpretation Act 1954, section 27A; and
              (b) does not apply to an original decision made by the chief executive officer.

              (4) If the review decision confirms the original decision, for the purpose of an appeal, the
              original decision is taken to be the review decision.

              (5) If the review decision amends the original decision, for the purpose of an appeal, the
              original decision as amended is taken to be the review decision.

              (6) In this section— review decision period means—
              (a) 15 business days after receiving an internal review application; or
              (b) another period agreed to between the distributor-retailer and the applicant.

              99BRBC Notice of review decision
              (1) The reviewer must, within 5 business days after the review decision period ends, give
              the applicant notice of the review decision (a review notice).

              (2) The review notice must state the reasons for the review decision.

              (3) If the review decision is not the decision sought by the applicant, the notice must also
              state the applicant may, within 20 business days after the review notice is given—
              (a) appeal against the decision to a building and development committee; or
              (b) appeal against the decision to the Planning and Environment Court.

              (4) If the reviewer does not comply with subsection (1), the reviewer is taken to have
              made a decision confirming the original decision.

              99BRBD Internal review stops particular actions
              (1) If an internal review is started under this division, any work under a water approval
              must not be started until the review is decided or withdrawn.




                                                                                                                                          Page 11 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Page 12

              (2) Despite subsection (1), if the reviewer is satisfied the outcome of the review would not
              be affected if the work is started before the review is decided, the reviewer may allow the
              work to start before the review is decided.

              Division 3 Appeals to a building and development committee

              99BRBE Appeals about applications for connections—general
              (1) This section applies to an applicant for a connection if—
              (a) for the application for a connection, the land to which the connection relates is subject
              to a development application mentioned in the Planning Act, section 519 or 522; and
              (b) the applicant applied for internal review of an approval decision or failure to decide;
              and
              (c) the review decision is not the decision sought by the applicant.

              (2) The applicant may appeal to a building and development committee against any of the
              following—
              (a) a refusal, or an approval in part, of an application;
              (b) a water approval condition;
              (c) another matter stated in the approval.

              (3) The appeal must be started within the standard appeal period.

              99BRBF Appeals about applications for connections—particular charges
              (1) This section applies to an applicant for a connection if—
              (a) the applicant applied for internal review of a charge decision or a decision to give an
              infrastructure charges notice; and
              (b) the review decision is not the decision sought by the applicant.

              (2) The applicant may appeal to a building and development committee about the review
              decision.

              (3) The appeal may be made only on 1 or more of the following grounds—
              (a) the decision involved an error relating to the application of the relevant charge;
              (b) if the decision is the giving of an infrastructure charges notice—
              (i) the decision involved an error relating to—
              (A) the working out, for section 99BRCJ, of additional demand; or
              (B) an offset or refund; or
              (ii) there was no decision about an offset or refund; or
              (iii) if the infrastructure charges notice states a refund will be given—the timing for giving
              the refund.

              (4) To remove any doubt, it is declared that the appeal must not be about—
              (a) the relevant charge itself; or
              (b) for a decision about an offset or refund for an infrastructure charges notice—
              (i) the establishment cost of infrastructure identified in the distributor-retailer’s water
              netserv plan; or
              (ii) the cost of infrastructure decided using the method included in the distributor-retailer’s
              infrastructure charges schedule.

              (5) The appeal must be started within the standard appeal period.

              99BRBFA Appeals against refusal of conversion application
              (1) This section applies to an applicant for a conversion application if—
              (a) the applicant applied for internal review of the conversion decision; and
              (b) the review decision is not the decision sought by the applicant.

                                                                                                                                          Page 12 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Page 13

              (2) The applicant may appeal to a building and development committee against the review
              decision.

              (3) The appeal must be started within the standard appeal period.

              99BRBG Application of relevant committee appeal provisions
              (1) The relevant committee appeal provisions apply, with any necessary changes, to an
              appeal under this division as if a reference in the provisions to—
              (a) an assessment manager were a reference to the distributor-retailer; and
              (b) a development application were a reference to the application for the water approval;
              and
              (c) a development approval were a reference to a water approval; and
              (d) an appeal under the Planning Act were an appeal under this Act; and
              (e) an infrastructure charges notice under the Planning Act were an infrastructure charges
              notice under this Act; and
              (f) the period required under the Planning Act for lodging a document to start proceedings
              were a reference to the period required under this Act for lodging a document to start
              proceedings.

              (2) In this section— relevant committee appeal provisions means—
              (a) the Planning Act, sections 536 to 537, 554 to 563, 564 (other than section 564(2)(d)
              and (e), 567, 569 and 569A; and
              (b) any definitions under that Act relevant to the sections mentioned in paragraph (a).

              99BRBH Notice of appeal
              (1) This section applies to an appeal under this division.

              (2) The registrar of building and development committees must, within 10 business days
              after the day the appeal is started, give written notice of an appeal under this division to
              the distributor-retailer.

              (3) The notice must state the grounds of the appeal.

              99BRBI Respondent for appeals
              (1) This section applies to an appeal under this division.

              (2) The distributor-retailer is the respondent for the appeal and may be heard in the
              appeal as a party to the appeal.

              99BRBJ Who must prove case for appeals
              In an appeal by the applicant under this division, it is for the applicant to establish that the
              appeal should be upheld.

              99BRBK Registrar must ask distributor-retailer for material in particular
              proceedings
              (1) This section applies to an appeal under—
              (a) section 99BRBE if the applicant applied for internal review of a failure to decide; or
              (b) section 99BRBFA if the applicant applied for internal review of a deemed refusal of a
              conversion application.

              (2) The registrar of building and development committees must ask the distributor-retailer
              to give the registrar—
              (a) all material, including plans and specifications, relevant to the application; and
              (b) a statement of the reasons the distributor-retailer had not decided the application
              during the period for deciding the application; and
              (c) any other information the registrar requires.
                                                                                                                                          Page 13 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Page 14

              (3) The distributor-retailer must give the material mentioned in subsection (2) within 10
              business days after the day the registrar asks for the material.

              99BRBL Lodging appeal stops particular actions
              (1) If an appeal is started under this division, any work under a water approval must not be
              started until the appeal is decided or withdrawn.

              (2) Despite subsection (1), if the building and development committee is satisfied the
              outcome of the appeal would not be affected if the work is started before the appeal is
              decided, the committee may allow the work to start before the appeal is decided.

              99BRBM Appeals may be combined with appeals under the Planning Act
              (1) This section applies if—
              (a) an appeal is started under this division; and
              (b) an appeal is started under the Planning Act for a development application mentioned
              in section 99BRBE.

              (2) The appeal under this division may be combined and heard with the appeal under the
              Planning Act.

              Division 4 Appeals to the Planning and Environment Court

              99BRBN Appeals about applications for connections—general
              (1) This section applies to an applicant for a connection if—
              (a) the applicant applied for internal review of an approval decision or failure to decide;
              and
              (b) the review decision is not the decision sought by the applicant.

              (2) The applicant may appeal against the review decision to the Planning and
              Environment Court.

              (3) The appeal must be started within the standard appeal period.

              99BRBO Appeals about applications for connections—particular charges
              (1) This section applies to an applicant for a connection if—
              (a) the applicant applied for internal review of a charge decision or a decision to give an
              infrastructure charges notice; and
              (b) the review decision is not the decision sought by the applicant.

              (2) The applicant may appeal against the review decision to the Planning and
              Environment Court.

              (3) An appeal under this section may be made only on 1 or more of the following
              grounds—
              (a) the charge imposed by the distributor-retailer is so unreasonable that no reasonable
              distributor-retailer could have imposed it;
              (b) the decision involved an error relating to the application of the relevant charge;
              (c) if the decision is the giving of an infrastructure charges notice—
              (i) the decision involved an error relating to—
              (A) the working out, for section 99BRCJ, of additional demand; or
              (B) an offset or refund; or
              (ii) there was no decision about an offset or refund; or
              (iii) if the infrastructure charges notice states a refund will be given—the timing for giving
              the refund.

                                                                                                                                          Page 14 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Page 15

              (4) To remove any doubt, it is declared that the appeal must not be about—
              (a) the relevant charge itself; or
              (b) for a decision about an offset or refund for an infrastructure charges notice—
              (i) the establishment cost of infrastructure identified in the distributor-retailer’s water
              netserv plan; or
              (ii) the cost of infrastructure decided using the method included in the distributor-retailer’s
              infrastructure charges schedule.

              (5) The appeal must be started within the standard appeal period.

              99BRBOA Appeals against refusal of conversion application
              (1) This section applies to an applicant for a conversion application if—
              (a) the applicant applied for internal review of the conversion decision; and
              (b) the review decision is not the decision sought by the applicant.

              (2) The applicant may appeal to the Planning and Environment Court against the review
              decision.

              (3) The appeal must be started within the standard appeal period.

              99BRBP Appeals about water connection compliance notices
              (1) This section applies if a person is given a compliance notice.

              (2) The person may appeal against the decision to the Planning and Environment Court.

              (3) The appeal must be started within 20 business days after the water connection
              compliance notice is given to the person.

              99BRBQ Application of relevant court provisions
              (1) The relevant court appeal provisions apply, with any necessary changes, to an appeal
              under this division as if a reference in the provisions to—
              (a) an appellant were a reference to the applicant; and
              (b) a respondent were a reference to the distributor-retailer; and
              (c) a development application were a reference to the application for the water approval;
              and
              (d) a development approval were a reference to the water approval; and
              (e) an appeal under the Planning Act were an appeal under this Act; and
              (f) an enforcement notice were a water connection compliance notice.

              (2) In this section— relevant court appeal provisions means—
              (a) the Planning Act, chapter 7, part 1, divisions 11 to 13 other than sections 482 to 490,
              493 and 495 (3) to (5); and
              (b) any definitions under that Act relevant to the provisions mentioned in paragraph (a).

              99BRBR Notice of appeal to other parties
              (1) The applicant must give notice of the appeal to the distributor-retailer.
              (2) The notice must be given within 10 business days after the appeal is started.
              (3) The notice must state the grounds of the appeal.

              99BRBS Stay of operation of water connection compliance notice
              (1) If the applicant gives a notice of appeal about a water connection compliance notice,
              the operation of the compliance notice is stayed until the earliest of the following to
              happen—
              (a) the Planning and Environment Court, on the application of the distributor-retailer,
              decides otherwise;
              (b) the appeal is withdrawn;
                                                                                                                                          Page 15 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

Page 16

              (c) the appeal is dismissed.


              (2) However, subsection (1) does not apply if the compliance notice is about—
              (a) a work, if the water connection compliance notice states the entity believes the work is
              a danger to persons or a risk to public health; or
              (b) stopping the demolition of a work; or
              (c) clearing vegetation on freehold land; or
              (d) the removal of quarry material allocated under the Water Act 2000; or
              (e) extracting clay, gravel, rock, sand or soil, not mentioned in paragraph (d), from
              Queensland waters; or
              (f) works the assessing authority reasonably believes is causing erosion or sedimentation;
              or
              (g) works the assessing authority reasonably believes is causing an environmental
              nuisance; or
              (h) action required to stop damage or further damage to the distributor-retailer’s water
              infrastructure.

              99BRBT Respondent for appeals
              The distributor-retailer is the respondent for the appeal and may be heard in the appeal as
              a party to the appeal.

              99BRBU Who must prove case for appeals
              In an appeal by the applicant under this division, it is for the applicant to establish that the
              appeal should be upheld.

              99BRBV Lodging appeal stops particular actions
              (1) If an appeal, other than an appeal under section 99BRBP, is started under this
              division, any work under a water approval must not be started until the appeal is decided
              or withdrawn.

              (2) Despite subsection (1), if the Planning and Environment Court is satisfied the outcome
              of the appeal would not be affected if the work is started before the appeal is decided, the
              court may allow the work to start before the appeal is decided.

              99BRBW Appeals may be combined with appeals under the Planning Act
              (1) This section applies if—
              (a) an appeal is started under this division; and
              (b) an appeal is started under the Planning Act for a development application which
              relates to land the subject of the application of a water approval.

              (2) The appeal under this division may be combined and heard with the appeal under the
              Planning Act.


              FOR MORE INFORMATION OR THE LATEST VERSION PLEASE REFER TO:

              https://www.legislation.qld.gov.au/LEGISLTN/CURRENT/S/SouthEQWDisA09.pdf




                                                                                                                                          Page 16 of 16
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015            Next Review Date:19/02/2018

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.