2016008949 DECISION NOTICE - Signed
Attached to the e-mail Operational Works Application OPW16/0338.
Connections Approvals Water Timing
CAW
Reticulated water supply
1
a) Provide reticulated water supply to the development, including a a) Prior to the
metered water service line and connection(s) to Unitywater’s issue of the
existing water supply network in accordance with Unitywater’s Certificate of
Connections Administration Manual & South East Queensland Completion.
Water Supply and Sewerage Design and Construction Code.
This condition is imposed under section 99BRDJ – conditions b) Prior to the
about non-trunk infrastructure of the South-East Queensland commencem
Water (Distribution and Retail Restructuring) Act 2009. ent of the
b) Engineering drawings and specifications detailing the works works.
required by this approval must be in accordance with Unitywater’s
South East Queensland Water Supply and Sewerage Design and c) Prior to the
Construction Code. issue of the
c) As-constructed drawings and data which detail the works Certificate of
constructed by the Applicant must be compiled and submitted in Completion.
accordance with Unitywater’s South East Queensland Water
Supply and Sewerage Design and Construction Code. d) At the time
d) The developer must pay all costs associated with the connection, the works are
inspection and acceptance of the proposed works. carried out.
Connections Approvals Sewer (CAS) Timing
CAS
Sewer reticulation
1
a) Provide reticulated sewerage to all lots within the development,
including a property connection to each lot and connection(s) to a) Prior to the
Unitywater’s existing sewerage network in accordance with issue of the
Unitywater’s Connections Administration Manual & South East Certificate of
Queensland Water Supply and Sewerage Design and Construction Completion
Code.
This condition is imposed under section 99BRDJ – conditions b) Prior to the
about non-trunk infrastructure of the South-East Queensland Water commencem
(Distribution and Retail Restructuring) Act 2009. ent of the
b) Engineering drawings and specifications detailing the works works
required by this approval must be in accordance with Unitywater’s
South East Queensland Water Supply and Sewerage Design and c) Prior to the
Construction Code. issue of the
c) As-constructed drawings and data which detail the works Certificate of
constructed by the Applicant must be compiled and submitted in Completion
accordance with Unitywater’s South East Queensland Water
Supply and Sewerage Design and Construction Code. d) At the time
d) The developer must pay all costs associated with the connection, the works are
inspection and acceptance of the proposed works. carried out
CAS
Sewer service connection points
2
Provide service connection points to all lots within the development. This Prior to the
condition is imposed under section 99BRDJ of the South-East Queensland issue of the
Water (Distribution and Retail Restructuring) Act 2009. Certificate of
Advice: The Applicant may request Unitywater to undertake these works Completion.
Page 3 of 16
Unitywater is a statutory authority that provides water and sewerage services for the Unitywater has certification to
OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas. Environmental ISO 14001:2004 Reg No 4259
Quality Systems ISO 9001:2008 Reg No 4258
Revision No: 2 Effective Date: 19/02/2015 Next Review Date:19/02/2018
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (2016008949 DECISION NOTICE - Signed.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.