Second Response to Information Request - 2 May 2018 · 132007.12.8
Attached to the e-mail 132007.12. 8 - Second Response to Information Request.
Court Appeals & Dispute Resolution
Applications & Assessment
Due Diligence & Compliance
Project Management
General Development Advice
Wednesday, 2nd May 2018
Our Ref: 14006
Council Ref: 132007.12.8
Chief Executive Officer
Noosa Council
PO Box 141
Tewantin QLD 4565
By Email: [email protected]
Attention: Lisa Pienaar, Development Planner
Dear Lisa,
Response to Information Request – ‘Other Changes’ Application for the ‘Noosaville
Medical and Professional Centre’ at 90 Goodchap Street, Noosaville described as Lot 3
on SP234909
Reference is made to the Information Request made by Council on 12 January 2018, and the
subsequent email received on 17 January 2018, raising some other issues. A response to the
Information Request was provided on 5 April 2018. Further, the application is currently being
publicly notified, which is due to finish on 10 May 2018.
Most of the issues raised in the Information Request have been responded to; however, the
applicant has obtained further advice from Thomson Geer with respect to the need to enter
into an infrastructure agreement. This is with respect to condition 631 of the current approval,
which states:
The applicant shall enter into an infrastructure agreement with Council with regard to the
provision of private services within the 5m wide road reserve that divides the two separate parts
of Lot 4 prior to the use commencing on the northern part of Lot 4. The conditions of the
infrastructure agreement shall:
a) Provide for the installation, maintenance and preservation of the private water and
electrical services that supply the separate parts of Lot 4;
b) Provide for the maintenance of the road reserve in those parts affected by the private
services;
1
Planning and Environment Court Judgement 3 February 2017
Adamson Town Planning Pty Ltd
(ACN: 163 798 374 | ABN: 73 163 798 374)
P (07) 5430 6671 F (07) 5430 6677 M 0437 754 420 Mail: PO Box 78, Peregian Beach QLD 4573
‘Noosa Boardroom’, 28 Eenie Creek Road, Nooosaville QLD 4566
Email| [email protected] Web| www.adamsontownplanning.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 2 pages
Page 2
“Adamson Town Planning, specialising in providing higher order town planning advice”
c) State that the applicant is responsible for obtaining approval for the design and
construction of the various services from the relevant authority;
d) State that the design and construction of the services shall be wholly at the applicant's
expense and shall not entail a financial encumbrance on future purchasers of the
proposed lot, and
e) Be to the satisfaction of the Department of Natural Resources and Water (DNR&W), If
DNR&W does riot consent to the private services crossing their land the applicant shall
find an alternative means of providing services to the balance of Lot 4 prior to the use
commencing.
The advice provided by Thomson Geer is provided as Attachment 1. The advice effectively
confirms that there is no need for an infrastructure agreement given the pathway bisecting
the land is within road reserve. This is because:
1) there is no necessity for the outcomes sought in Condition 63 to be imposed by way of
infrastructure agreement, because:
(a) it is lawful for the Council to impose conditions requiring works in the existing public
roadway and for the works to be undertaken at the applicant's cost; and
(b) it is lawful for the Council to impose conditions requiring the ongoing maintenance of
those services;
2) it is in fact less desirable for the parties to enter into an infrastructure agreement (as
contemplated by the condition), particularly from the point of view of Council, given:
(a) there are costs associated with drafting, reviewing and then implementing an
infrastructure agreement (for both parties) that can be readily avoided by utilising a
condition of approval;
(b) Condition 63, already requires the applicant to seek further approvals for operational
work and there is an ability for the Council to appropriately condition any detailed
requirements that may be necessary for the works, which means that an infrastructure
agreement adds nothing to the process;
(c) a condition of approval provides greater clarity and certainty moving forward, as future
owners of the development can be expected to be aware of the conditions associated
with an approval but are less likely to be aware of a related infrastructure agreement.
It is also noted that Thomson Geer has advised that the condition was imposed during the
currency of the Integrated Planning Act 1997. At the time it was imposed it was lawful to
impose a condition that mandated an applicant to enter into an infrastructure agreement;
however, such conditions are no longer lawful and are expressly prohibited by section 66(1)(b)
Planning Act 2016. Consequently, it is requested that condition 63 be amended as follows:
With regard to the provision of private services within the 5m wide road reserve that divides the
two separate parts of Lot 3 on SP264909, prior to the use commencing on the north western part
of Lot 3, the applicant shall:
a) provide for the installation, maintenance and preservation of the private water and
electrical services that supply the separate parts of Lot 3;
2|Page
14006 – Noosaville Medical and Professional Centre, New Office and Carpark Structure
Page 3
“Adamson Town Planning, specialising in providing higher order town planning advice”
b) provide for the maintenance of the road reserve in those parts affected by the private
services;
c) be responsible for obtaining approval for the design and construction of the various
services from the relevant authority;
d) undertake the design and construction of the services at the applicant's expense and shall
not entail a financial encumbrance on future purchasers; and
e) undertake all works to the reasonable satisfaction of the Council.
It requested as part of the current ‘other changes’ application, that Council amend condition
63 as suggested above and remove the requirement for an infrastructure agreement. This is
because an infrastructure agreement is not necessary, with the design, construction and
maintenance of private infrastructure by the applicant able to be dealt with by a condition of
approval as is normally the case. Further, the cost of the preparation, review and
implementation of an infrastructure agreement can be avoided for both Council and the
applicant.
Should you have any questions with respect to the above, please contact me.
Yours faithfully
Shane Adamson (BEngTech, GDURP, MPIA)
Town Planning Specialist
Director - Adamson Town Planning Pty Ltd
3|Page
14006 – Noosaville Medical and Professional Centre, New Office and Carpark Structure
Used in these records
Second Response to Information Request - 2 May 2018.pdfRelated documentApplication case desk ↗
About this file
- File size
- 232 KB (small file)
- File type
No other editions are linked here.