c) State that the applicant is responsible for obtaining approval for the design and
construction of the various services from the relevant authority;
d) State that the design and construction of the services shall be wholly at the applicant's
expense and shall not entail a financial encumbrance on future purchasers of the
proposed lot, and
e) Be to the satisfaction of the Department of Natural Resources and Water (DNR&W), If
DNR&W does riot consent to the private services crossing their land the applicant shall
find an alternative means of providing services to the balance of Lot 4 prior to the use
commencing.
The advice provided by Thomson Geer is provided as Attachment 1. The advice effectively
confirms that there is no need for an infrastructure agreement given the pathway bisecting
the land is within road reserve. This is because:
1) there is no necessity for the outcomes sought in Condition 63 to be imposed by way of
infrastructure agreement, because:
(a) it is lawful for the Council to impose conditions requiring works in the existing public
roadway and for the works to be undertaken at the applicant's cost; and
(b) it is lawful for the Council to impose conditions requiring the ongoing maintenance of
those services;
2) it is in fact less desirable for the parties to enter into an infrastructure agreement (as
contemplated by the condition), particularly from the point of view of Council, given:
(a) there are costs associated with drafting, reviewing and then implementing an
infrastructure agreement (for both parties) that can be readily avoided by utilising a
condition of approval;
(b) Condition 63, already requires the applicant to seek further approvals for operational
work and there is an ability for the Council to appropriately condition any detailed
requirements that may be necessary for the works, which means that an infrastructure
agreement adds nothing to the process;
(c) a condition of approval provides greater clarity and certainty moving forward, as future
owners of the development can be expected to be aware of the conditions associated
with an approval but are less likely to be aware of a related infrastructure agreement.
It is also noted that Thomson Geer has advised that the condition was imposed during the
currency of the Integrated Planning Act 1997. At the time it was imposed it was lawful to
impose a condition that mandated an applicant to enter into an infrastructure agreement;
however, such conditions are no longer lawful and are expressly prohibited by section 66(1)(b)
Planning Act 2016. Consequently, it is requested that condition 63 be amended as follows:
With regard to the provision of private services within the 5m wide road reserve that divides the
two separate parts of Lot 3 on SP264909, prior to the use commencing on the north western part
of Lot 3, the applicant shall:
a) provide for the installation, maintenance and preservation of the private water and
electrical services that supply the separate parts of Lot 3;
2|Page
14006 – Noosaville Medical and Professional Centre, New Office and Carpark Structure
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Second Response to Information Request - 2 May 2018.pdfRelated documentApplication case desk ↗
About this file
- File size
- 232 KB (small file)
- File type
No other editions are linked here.