36. A stormwater quality treatment system must be provided for the development. The works
must be undertaken in accordance with the Bioretention Technical Design Guidelines (Water
by Design, 2012), and must include in particular stormwater quality treatment devices of a
size and location generally in accordance with the approved engineering operational works
plans as prepared by Morgan Consulting Engineers.
Assessment of Request
The requested amendment was referred to development engineering for consideration.
Development engineering advise;
The proposed engineering related changes include:
1. A deck extension to the Unit 6 terrace spanning across the proposed stone pitched swale;
2. Replacement of the Unit 8 terrace with a deck spanning across the level spreader /
stormwater discharge location;
3. Re-configuration of the bio-retention basin resulting in an increase of the bio-retention
area from 9m² to 16m².
A site inspection confirmed that construction has occurred at the site regarding the enlargement
level spreader and bio retention area. The bio-retention basin results in an increase area from 9m²
to 16m². It is unclear why the inconsistency between the approved plans and the constructed
infrastructure has occurred however the works do not impact the functioning of the stormwater
design approved for the development consistent with Council’s Planning Scheme Policy - SC6.7.6
Stormwater Management.
Plans relevant to the MCU have been amended to ensure maintenance of the bio retention area
can occur via common property and as such Council support the proposed changes.
Recommendation
Agree. It is recommended existing conditions 34 and 35 be amended as follows.
Stormwater Drainage
34. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge and be in accordance with the Queensland Urban Drainage Manual (QUDM). The
works must be undertaken in accordance with an Operational Works approval and include in
particular:
a) The works generally as shown in accordance with on concept plan 23098/SK10
Revision G the approved engineering operational works plans as prepared by Morgan
Consulting Engineers.
b) Collection and lawful discharge of stormwater to ensure that adjoining properties,
reserves and roads are protected from ponding or actionable nuisance from stormwater
as a result of any works undertaken.
c) The site stormwater system is to accommodate stormwater from Lot 1 RP153798
external to the site, including registration of drainage easements over the site drainage
system in favour of Lot 1 RP153798.
d) the use of gravity stormwater drainage and not surcharge pits
35. A stormwater quality treatment system must be provided for the development. The works
must be undertaken in accordance with the Bioretention Technical Design Guidelines (Water
by Design, 2012), and must include in particular stormwater quality treatment devices of a
Page 15 of 29
Document Set ID: 24138568
Version: 7, Version Date: 17/04/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Report MCU21 0117 02 (As Published).pdfRelated documentApplication case desk ↗
Minor Change Report MCU21 0117 02 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.7 MB (small file)
- File type
No other editions are linked here.