7 Noise & odour management
7.1 Responsibility
The Project Manager is responsible for ensuring the appropriate management of noise and odour during
dewatering operations.
7.2 Operational policy
To minimise noise and odour emissions generated from the site during dewatering.
7.3 Performance criteria
The appropriate criteria to measure the performance of dewatering management at the site are provided
below.
1. No noise or odour related complaints received from neighbouring residents or the community.
2. No degradation of air quality due to fumes or odours emanating from the dewatering process.
7.4 Implementation strategy
Noise and odour emissions will be managed as described in the following sections.
7.4.1 Noise
All dewatering equipment must be operated appropriately and maintained in good working order. All
dewatering systems and plant must be fitted with the appropriate noise reduction equipment to comply
with the performance criteria. Non‐complying dewatering plant will be replaced or repaired as necessary.
7.4.2 Odour
All dewatering plant must be fitted with the appropriate emission reduction devices. Where practicable,
all dewatering plant will be sealed to prevent the release of odours to the atmosphere. Fine mist odour
control sprays will be applied to reduce offensive odours if complaints are received from neighbouring
residents.
7.5 Monitoring
An inspection of the site and dewatering equipment shall be undertaken daily by the Site Manager to
identify the following:
Excessive noise being generated by the dewatering systems and plant; and
Strong or offensive odours being generated by the dewatering equipment and/or extracted
groundwater.
7.6 Reporting
Reporting will be undertaken as described in Section 6.7 of this report.
7.7 Contingencies
If noise levels consistently exceed the performance criteria, temporary acoustic barriers will be
constructed around the offending dewatering systems and plant. Odour control sprays will be applied as
necessary to mask odour emissions if complaints are received from neighbouring residents. This may
include the direct injection of deodorisers to the groundwater treatment system.
ADG1304.21 Dewatering Management Plan_Rev0_08.10.21 Page 17
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Dewatering Management Plan.pdfRelated documentApplication case desk ↗
Dewatering Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 9.0 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.