. Amendment to the layout to accommodate the relocated Twigrush Basin. This basin results in a
’link road’ which is located north of the basin. Through access from Twigrush Court to Shire Drive
is no longer anticipated;
. Minor boundary amendments to accommodate the Twigrush Basin and Basins B1A and B1C.
The boundaries of adjacent allotments have been shuffled to accommodate the basins whilst still
maintaining overall yield. It is advised that some lots have been necessarily reduced in area in
order to achieve this outcome, although we note that a minimum lot size of 600m2 is still achieved.
This minimum lot size is in accordance with the requirements of the planning scheme (and
condition 70 of the approval), and was confirmed with Council at our meeting of 20 February 2013
that should this minimum lot size continue to be achieved that there would be no fundamental
concern with reconfiguring the layout in the manner proposed; and
. Amendments to developable footprint to accommodate pedestrian paths and maintenance access
around the basins.
In addition to the above, changes to the staging and minor changes to the road configuration are also
sought. These changes represent a minor amendment to the changes sought as part of the original
’permissible change request’ package, and include the following:-
. The configuration of Lots 177 to 181 have been amended to return to the original cul-de-sac
design;
. Stage B3 has been sub-staged into 2 stages, comprising stages B3 and B4. It is anticipated that
Stage B3 will be delivered first given anticipated timing of sewer services;
.
Stage C3 and part of Stage C1 has been sub-staged into C1 and C2. It is noted that the public
open space, ’link road’ and two basins are included within new stage C1. As previously advised
to Council (email dated XXX), our client is prepared to accept the delivery of new Stage C1 as the
first component of Stage C to be delivered; however, would like to reserve the right to develop the
remaining stages in any order subject to market conditions. Notes on the face of the ’Staging’
Plan (6812-61R) and ’Staging & Lot Summary’ Plan (6812-1620)reflects this.
. Stage C2 has been sub-staged into C3 and C5;
. Part of stage C1 has been included within Stage C4 and previous Stage C4 has been renamed
Stage C6. It is noted that proposed basin B1 C is included within new Stage C4 and proposed
basin B1A is included within Stage C6 as the catchment to which these basins relate are
new
predominantly related to these new Stages.
In order to reflect the above changes to the layout, we recognise that the following conditions and I or
Advisory Notes will need to be amended:-
. Condition 1 -
new version of the Plan of Development: 6812-58J;
. Condition 25 -
the plan number to be updated to: 6812-66E;
. Condition 65.1 -
new version of the plan of Proposed Reconfiguration for non-scheme lots: 6812-
60F, comprising four (4)sheets;
Page 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Further information re Request to Change Approval MCU 132003.221132.8Related documentApplication case desk ↗
About this file
- File size
- 39.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.