2009/695
2.1. The plan should detail the routing of trucks to and from the site, in particular the load
limit of 9 tonnes on Park Road.
2.2. Provision of onsite parking for personnel working on this development, as there is
limited parking available in adjacent streets.
2.3. Provision of safe cycle and pedestrian movements in the vicinity of the development
on Little Cove Road.
2.4. No queuing of trucks is permitted on residential streets, especially prior to 7.00am.
Further parked trucks must have engines turned off.
2.5. Provision of signage and traffic controllers in accordance with Manual of Uniform
Traffic Control Devices and Transport Infrastructure (Roads) Act.
3. Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily
installed into the first existing external downstream stormwater structure.
These devices are to be checked and cleaned on a regular basis and specifically after each
rain event.
These devices are to remain in place during the civil works and construction phases of the
development.
The location and type of device to be installed shall be established at the “pre start” meeting
with Council’s Construction Technical Officer and shall be installed prior to the
commencement of any works.
4. A site control and/or compliance bond of $1000 is to be submitted to Council prior to the pre-
start meeting. The pre-start meeting will only be held once Council's Construction Technical
Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
5. Council’s Construction Technical Officer (ph 0410 512 505), shall be given seven (7) days’
notice of intention to commence works to arrange a “pre start” meeting prior to the
commencement of works.
6. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to ensure
that any sub contractors also have the appropriate insurance and public liability
documentation.
7. Prior to the “pre start” meeting, the principal contractor must be provided with a copy
of Council’s signed approved drawings and conditions by the applicant.
8. The Consulting Engineers for the project shall be currently Registered Professional Engineers
of Queensland (RPEQ). The Consulting Engineers are responsible for arranging all
inspections with Council’s Construction Technical Officer or nominated staff.
9. Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
project. (This person will be the contact for the project).
10. Council standards shall apply to these works unless otherwise modified herein.
11. The person acting on this permit shall ensure that its consultants and contractors take all
reasonable care during the construction of the engineering works to ensure that Council
property, road pavements or facilities (such as underground drainage, water supply,
sewerage, footpaths, kerbing, landscaping, street furniture etc.) are protected against any
damage or interference whatsoever.
Page 2 of 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
001ACB27.001.pdfRelated documentPublic source context ↗
Decision Notice - 010.2009.00000695.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 56 KB (small file)
- File type
No other editions are linked here.