               76.    Prior to the completion of the development, all site surfaces must be effectively stabilised.
                      For the purpose of this condition, an effectively stabilised surface is defined as one that does
                      not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully
                      erosion or lead to sedimentation, or lead to water contamination.
               FOLLOWING CONSTRUCTION
                      Certification
               77.    Upon completion of the work and prior to the final inspection a certificate must be issued by
                      an RPEQ certifying that the works have been constructed in accordance with the Operational
                      Works permit and applicable engineering standards.
               78.    A final inspection and approval of the completed works by Council’s Inspector is required.
                      Please contact Council on 5329 6245 to arrange for the inspection.
               79.    All stormwater quality treatment devices must be maintained in accordance with the Water
                      by Design (2009) - Maintaining Vegetated Stormwater Assets (Version 1). A copy of this
                      document must be retained on the site together with the approved Operational Works
                      drawings for the stormwater quality treatment system and a detailed life cycle costing of the
                      system attached as an addendum. Records of all maintenance activities undertaken must
                      be kept and made available to Council upon request.
               80.    Any proposed Community Management Statement required for the development must
                      include the Water by Design (2009) – Maintaining Vegetated Stormwater Assets (Version 1)
                      document and must include the full cost of maintaining the system in accordance with that
                      document.
               81.    The areas identified as ‘Loading bay 3’ and ‘Loading bay 4’ in the Site Plan No. DA01 Rev.
                      7 and dated 13 March 2018, are to be used solely for truck loading and manoeuvring
                      purposes and must remain clear of obstructions at all times. These areas are not to be used
                      for any fabrication, assembly, storage or other purposes.
               82.    The loading and manoeuvring areas within the building must be line marked, sign posted and
                      pavement marked ‘Keep Clear’ in accordance with the areas described by ‘Loading bay 3’
                      and ‘Loading bay 4’ on Site Plan DA01 Rev 7 and dated 13 March 2018
               MATERIAL CHANGE OF USE - MCU17/0568.01 – Additional Conditions – 3 October 2023
               83.    The display eco cottage is to be temporary and used for display only. It is not to be used as
                      an office.
               84.    The rear access as proposed on Site Plan, drawn by Eco Cottages dated 21 February 2023
                      and Site Plan – Landscape Added, drawn by Eco Cottages dated 19 June 2023 is not
                      approved. No vehicular access is to be gained from the rear of the site.
                      Water Sensitive Design
               85.    The proposed works (pedestrian foot bridge, showroom) must not adversely affect the
                      treatment capabilities or the structural integrity of any component of the existing bioretention
                      basin.
               86.    The supervising RPEQ must certify that the proposed works (pedestrian foot bridge,
                      showroom) has not adversely affected the treatment capabilities and structural integrity of
                      the existing bioretention basin. Certification must be provided and accepted by Council at the
                      completion of the works.
               5.     REFERRAL AGENCIES

               Not applicable.




                                                                                                      Page 11 of 15
Document Set ID: 22608628
Version: 4, Version Date: 05/10/2023
Log in to download the original file

Minor Change - MCU17 0568 01 & OPW17 0602 01 [As Published].pdf · 214 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.