Original source · versioned page text
Minor Change - MCU17 0568 01 & OPW17 0602 01 [As Published]
ii. Fencing to the work site during the construction phase to ensure the safety of the
public and the road users.
iii. Maintenance of safe pedestrians and cyclists access across the frontage of the
site both during daily construction and after daily construction has ceased.
iv. Sufficient parking arrangements for trucks, machineries and construction workers
without adversely impacting on traffic flow and/or the availability of on-street
parking in the local street.
b) Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures.
c) Works programme identifying key components of the works and their respective
durations.
d) The proposed dates for the commencement and the completion of the works.
e) Effective procedures and measures to minimise adverse environmental impact on
other properties and roads users including noise and dust emission.
f) Establishment of a communication protocol with the adjoining owners and any other
affected parties to advise of construction times, impacts on traffic and services and any
other relevant issues.
g) Identification of communication and complaint management procedures including:
i. Contact details for the on-site manager.
ii. Dispute resolution procedures.
36. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
37. Any alteration to existing services or conflict between the development and an existing or
proposed service must be referred to the relevant service authority for determination prior to
commencement of works.
DURING CONSTRUCTION
General
38. The developer must meet any costs to repair damage to any Council’s and/or public asset
during construction, where damage is a result of the development works. Damage to assets
must be repaired immediately where it creates a hazard to the community. In circumstances
where the damage does not create a hazard to the community, it must be repaired
immediately on completion of the works associated with the development.
39. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works (eg public pathway)
are involved, such confirmation must be submitted for the respective hold points prior to any
site inspection by Council Officers.
40. All works must be constructed and work procedure undertaken in accordance with:
a) The approved plans and conditions detailed in this Decision Notice.
b) All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines, particularly PSP 5 – Engineering Design Standards –
Roads, Drainage and Earthworks.
c) The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Page 6 of 15
Document Set ID: 22608628
Version: 4, Version Date: 05/10/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original