               OPERATIONAL WORKS - OPW17/0602
               APPROVED PLANS
               28.    Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                        Plan No.           Rev.   Plan/Document Name                               Date
                        27281-OW5          B      Operational Works: Driveway & Access,            13.02.2018
                                                  prepared by SCG Consulting Engineers
                        27281-SW1          C      Operational Works Stormwater Management,         22.02.2018
                                                  prepared by SCG Consulting Engineers

               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               29.    At least 5 working days prior to any works commencing, written advice must be provided to
                      Council detailing:
                      a)      The name, contact details and ACN for the supervising Registered Professional
                              Engineer of Queensland (RPEQ) and Principal Contractor.
                      b)      Proposed dates for commencement and completion of construction.
               30.    The principal contractor must have all the appropriate insurance and public liability
                      documentation to carry out the works. The principal contractor is also responsible to ensure
                      that any subcontractors also have the appropriate insurance and public liability
                      documentation. Certificates demonstrating currency of public liability insurance and works
                      insurance covering the works must be submitted to Council prior to the prestart meeting.
               31.    Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart meeting*. The contact number to arrange a prestart meeting is 5329
                      6244. The prestart meeting must include the relevant parties for the following aspects of the
                      works:
                      a)      Civil engineering and stormwater drainage works.
                      b)      Landscape works.
                      c)      Erosion and sediment control works.
                      * (Refer to Advisory Note)
               32.    Copies of the approved plans, duly signed by the consultant Registered Professional
                      Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer at the
                      “prestart” meeting.
               33.    A detailed condition report including photographs of all frontages of the site must be
                      completed and submitted to Council prior to the prestart meeting.
               34.    A condition report including photographs of all fences and retaining walls bordering the site
                      and any buildings, structures, pathways, landscaping features etc on adjoining properties
                      that could potentially be impacted on by the proposed earthworks and construction works
                      must be completed and submitted to Council prior to the prestart meeting.
               35.    A Construction Management Plan must be submitted to Council for approval prior to the
                      prestart meeting and must specifically include/address the following:
                      a)      Traffic Management during all aspects of the construct phase including:
                                i.     A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures to be installed prior to construction.



                                                                                                        Page 5 of 15
Document Set ID: 22608628
Version: 4, Version Date: 05/10/2023
Log in to download the original file

Minor Change - MCU17 0568 01 & OPW17 0602 01 [As Published].pdf · 214 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.