ORDINARY MEETING MINUTES 17 MAY 2018
b. 1.50-metre-wide landscaping strip on the Eumundi Noosa road reserve frontage
adjacent to the landscaping within the site, exclusive of the access driveway,
generally uncompromised by infrastructure items, except for the eastern side of
the entry crossover.
c. Provision of 1 street tree within the road reserve west of the exit crossover, the
tree must be a local native species.
d. Provision of landscaping on the adjoining Council reserve (Lot 22 RP881370).
The landscaping must be at least one metre wide and be provided adjacent to
the common boundary between the existing tree and the front boundary.
28 All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
29 All landscape works must be maintained generally in accordance with the approved
design for the life of the development.
ENVIRONMENTAL HEALTH
Underground tanks
30 Prior to the commencement of the use underground tanks shall be constructed and
installed in accordance with the following:
a. Tanks are to be made of fibre-reinforced thermosetting resin (fibreglass) that is
compatible with the product or tanks are to be made of a steel inner wall and a
fibre-reinforced thermosetting resin composite (fibreglass) outer wall.
b. Tanks are to be double-walled with an interstitial space.
c. Tanks are to meet the requirements of UL 1316 Glass fibre reinforced
underground storage tanks for petroleum products, alcohols and alcohol gasoline
mixtures, or the equivalent or tanks are to meet the requirements of AS1692-
2006 Steel tanks for flammable and combustible liquids, or the equivalent.
d. Tanks are to have an overfill protection valve installed in the drop tube of the
tank. The overfill prevention valve shall be calibrated to prevent the tank from
being filled in excess of 90% of its capacity.
Submit certification
31 Prior to the commencement of the use certification by a suitably qualified person that
the underground tanks have been constructed and installed in accordance with the
above requirements must be submitted to Council.
Pipework
32 Prior to the commencement of the use pipework shall be constructed and installed in
compliance/accordance with the following:
a. Pipework is to be made of non-corrodible materials as defined by cl 1.4.37 AS
4897. The design, installation and operation of underground petroleum storage
systems.
b. Product piping is to be double-walled with an interstitial space.
c. Each tank fill point is to be clearly labelled and identified in accordance with AS
4977 Petroleum products - Pipeline, road tanker compartment and underground
tank identification.
d. Each tank fill point is to be fitted with a camlock type or other liquid-tight
connection.
Page 23 of 30