13. A final Construction Management Plan must be submitted to Council prior to the pre-start
meeting. The plan must be generally in accordance with the Construction Management Plan
prepared by Barlow Shelley ref:1856-CMP-01 Version 2.0 dated October 2020 and include
the following amendments/additions:
a. Section 2.3
i. Working Hours
ii. Written approval must be obtained from Council prior to any works outside of the
approved operating hours
iii. No works are permitted on Sundays
b. Section 2.4
i. Amend the commencement date
c. Section 4.1
i. include “No queuing of trucks is permitted on residential streets, especially prior
to 7.00am. Further parked trucks must have engines turned off”
ii. include details on the location of external fill/dump sites/sources, the haulage
route, type of vehicle to be utilised during filling operations and frequency of
usage.
iii. include NB: any damage to the existing road system as a result of haulage
operations shall be fully repaired at the applicant’s expense
d. Section 4.12
i. include establishment of a communication protocol with the general public,
adjoining owners, emergency services and local businesses to advise of agreed
construction times, impacts on traffic and services and other relevant issues
ii. include a post out to the local residents and business advising of the proposed
development, the expected time frames and the site contact details
iii. include signage in prominent locations on the boundaries of the site advising of
the proposed development, the expected time frames and the site contact details
iv. include signage/displays in prominent locations within the adjacent shopping
centre advising of the proposed development, the expected time frames and the
site contact details
14. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
15. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
Environment
16. Provide written evidence of Council’s receipt of monies required by Clause 4 of the
Environmental Offset Agreement.
17. Ensure all retained vegetation is clearly marked out on site for inspection by Council’s
delegate
18. Provide to Council for review a staged clearing plan, endorsed by the fauna consultant to
comply with fauna management requirements in this permit.
19. Provide to Council the written findings of the fauna consultant’s pre-clearing trapping works.
Page 14 of 35
Document Set ID: 24395463
Version: 4, Version Date: 03/02/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice OPW20 145 06 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 957 KB (small file)
- File type
No other editions are linked here.