210319_approval
Attached to the e-mail RE Operational works application for 41 Sunshine Beach Road MCU 20 0136.msg.
Noosa Council documents
Water & Sewer Connections
25. An underground connection to reticulated water and sewerage must be provided to the
development site in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
26. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
must be submitted to Council that certifies an underground connection to reticulated water
and sewerage has been provided to the development site.
Weather Protection
27. Street awnings must be provided along the full length of the Sunshine Beach Road and
Berrima Row frontages as shown on the approved plans. The awnings must have a minimum
width of 3.2 metres from the building line unless otherwise approved, and must be designed
to provide continuous solar and rain protection and promote all weather activity.
Public Safety
28. All ground floor shopfront glazing must be protected against vandalism by the use of a form
of safety glass such as toughened or laminated glass.
29. During operating hours, all parking areas, pedestrian areas and entrances/exits to all
stairwells, lifts, foyers and public toilets must be well lit with vandal resistant lighting and with
intensities to satisfy the requirements of Australian Standard AS1158 “Public Lighting Code”.
Lighting must be designed to reduce the contrast between shadows and well lit areas. In
particular, appropriate security lighting must be provided in the location of the bicycle/ scooter
parking and bin storage area.
30. After hours access to loading docks, storage areas and the basement carpark (including the
vehicle ramp and all stairwells) must be restricted by a security gate, lockable doors and/or
other suitably appropriate means. The basement carpark must be kept closed and locked at
all times while the use is not operating.
Community Management Statement
31. Any proposed Community Management Statement required for the development pursuant to
the Body Corporate and Community Management Act 1997 must be submitted to Council for
endorsement at the same time as submission of the Building Format Plan (or similar) to
Council for compliance assessment.
32. All clauses and by-laws of the proposed Community Management Statement must accord
with the requirements of this Decision Notice.
Site Access and Driveways
33. A sealed access driveway must be provided from Berrima Row to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance with
an Operational Works approval and must include in particular:
a. a driveway crossover generally in accordance Council’s standard drawing RS-051and
respective addendum;
b. a driveway crossover generally in accordance with SCG’s plan 30292-C2, titled
“Driveway Access Plan”, dated November 2020;
c. suitable safety measures, including warning signage, to improve driver awareness of
pedestrians and enhance pedestrian safety. Warning signage must be provided near
the exit ramp from the underground parking area to warn motorists of pedestrian
movement along the frontage street;
d. the footpath’s section of the driveway must be the same colour as the existing footpath
(i.e. terracotta or similar).
Page 4 of 11
Document Set ID: 21417355
Version: 6, Version Date: 18/03/2021 Print Date: 18 March 2021, 4:14 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (210319_approval.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.