                      Car Parking
               34.    A minimum of 9 car parking spaces must be provided and marked on the site. The works
                      must be undertaken in accordance with an Operational Works approval and must include in
                      particular:
                      a.      4 staff parking spaces within the total, which are clearly marked for that purpose
                      b.       1 disabled parking space within the total
                      c.      dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
                              Parking Facilities
               35.    All car parking areas and access driveways must be maintained exclusively for vehicle
                      parking and manoeuvring and kept in a tidy and safe condition at all times.
                      Security Access to Carpark
               36.    Where access to the carpark is proposed to be restricted by a security gate, provision must
                      be made for queuing of vehicles clear of the roadway while waiting for the security gate to
                      open.
                      Pedestrian and Bicycle Facilities
               37.    Pedestrian and bicycle facilities must be provided for the development. The works must be
                      undertaken in accordance with an Operational Works approval and must include in particular:
                      a.      adequate separation of all specific pedestrian routes from vehicle access and
                              manoeuvring areas, and clear demarcation by pavement marking, signposts or
                              changes in surface materials or levels
                      b.      signage and lighting at strategic locations to direct people to building entries;
                      c.      a total of 6 bicycle parking spaces
                      d.      end of trip facilities involving 4 lockers, at least 1 male and female showers and change
                              rooms.
                      Stormwater Drainage
               38.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken in accordance with an Operational Works
                      approval and generally in accordance with SCG’s plan 30292-C4, Rev A, titled “Stormwater
                      Management Plan”, dated 18/01/2021.
                      Services
               39.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               40.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater) which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.
                      Easements
               41.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               42.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               43.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.



                                                                                                           Page 5 of 11
Document Set ID: 21417355
Version: 6, Version Date: 18/03/2021                                                                   Print Date: 18 March 2021, 4:14 PM

Log in to download the original (210319_approval.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.