GENERAL COMMITTEE MEETING AGENDA 13 JUNE 2022
Page 43 of 69
GENERAL COMMITTEE MEETING AGENDA 13 JUNE 2022
Attachment 1 Noosa Spit Dredging & Beach Nourishment Tender Consideration Plan
Background:
Council has committed to the completion of the Noosa Spit Dredging & Beach Nourishment works
(Dog Beach).
The Infrastructure Department has obtained the required environmental permit to complete the
dredging and nourishment works. The dredging works however must be completed by September
30" to comply with the permit’s conditions. This leaves only a very small window to engage a
specialist contractor and complete all the required dredging works.
The effectiveness of the beach renourishment and river channel dredging will be dependent on the
completeness of the designed dredging works.
Operative Provisions:
1. DEFINITIONS AND INTERPRETATION
1.1 Definitions
In this Tender Consideration Plan, unless inconsistent with the context or subject matter:
(a) Act means the Loca/ Government Act 2009;
(b) Council means Noosa Shire Council;
(c) Objectives means the objective set out in Clause 2 of this Tender Consideration
Plan;
(d) Regulation means the Loca/ Government Regulation 2012;
(e) Tender Consideration Plan means this tender consideration plan, which Council
has prepared and adopted pursuant to section 230 of the Regulation.
2. OBJECTIVES OF THE TENDER CONSIDERATION PLAN
2.1 The objective of this Tender Consideration Plan (TCP) is to enter into a contract with a
selected contractor for the completion of works for the Noosa Spit Dredging and Beach
Nourishment, within the parameters and timeframes of the environment permit issued by
Department of Environment and Science.
2.2 It is proposed that the establishment of this contract be via a competitive Invitation to
Quote (ITQ) process to contractors identified as a result of market analysis, as outlined in
Section 7 of this TCP.
2.3 In accordance with the permit that has been granted to Council, there is a specified
window of opportunity for the works to be completed. It is anticipated that establishing a
Page 3 of 6
Page 43 of 69See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.