GENERAL COMMITTEE MEETING AGENDA 13 JUNE 2022
Page 44 of 69
GENERAL COMMITTEE MEETING AGENDA 13 JUNE 2022
Attachment 1 Noosa Spit Dredging & Beach Nourishment Tender Consideration Plan
contract on or before by 24 June 2022, as a result of this TCP, will provide Council the
best opportunity of completing the works within this window.
The longer the duration that a contractor has to complete the works the greater flexibility
the contractor has for machinary selection, potentially lowering construction cost, program
resiliance to delay due to breakdown or inclement weather/river contitions, and a better
opportunity to ensure a quality finish of the the beaches nourishment.
3. HOW THE OBJECTIVES ARE TO BE ACHIEVED
3.1 The Objectives will be achieved by:
(a) Inviting written quotations from identified contractors that Council considers are
capable of delivering the required services within the timeframes, and assessing
those quotations against the following weighted criteria:
Capability, Resourcing, Contract
Experience
Methodolog
[Quality 5%
Health and Safet
Environment and Sustainabilit
Contribution to Local Econom
(b) As a result of a market analysis and given the time pressures for this project an
Invitation to Quote (ITQ) has been issued to three (3) identified contractors as
follows:
e Rimlex Pty Ltd t/a Nabis Dredging,
e Hall Contracting Pty Ltd , and
e Neumann Contractors Pty Ltd,
The ITQ has been issued advising that any resutling contract will be subject to
evaluation of responses against the criteria outlined in this TCP and Council
resolving to adopt this TCP.
4. HOW THE ACHIEVEMENT OF THE OBJECTIVES WILL BE MEASURED
4.1 Value for Money
Council will:
(a) Undertake market analysis of identified dredging contractors to determine
availability/capacity to undertake the works, and subsequently issue the ITQ to
those that confirm (refer Section 7 below),
(b) Evaluate the Invitation to Quote (ITQ) responses against the criteria out lined 3.1
(a) above,
(c) Determine Value for Money, as a result of ITQ evaluation and in particular the
quotation breakdowns, against the allocated budget.
Page 4 of 6
Page 44 of 69See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.