Council archive · source document
Delegated Report - Code - Planning MCU23 0134 · MCU23/0134
2. The Currency Period for this development approval lapses if all conditions have not been
complied with by 19 January 2026, unless an application to extend the currency period is
approved by Council.
Performance Bond
3. Security in the form of a cash bond or trading bank guarantee to the sum of $5000 must be
submitted to Council, to secure performance of all conditions of this approval, prior to the
commencement of the works. The cash bond or trading bank guarantee will be returned on
performance of the conditions of this approval less any costs incurred by Council in respect
of enforcing performance of this permit. Council reserves the right to call upon the bond or
guaranteed sum to effect compliance with conditions.
General Conditions
4. The maximum number of vessels that may be berthed, moored, attached or stored on the
structure must not exceed 2.
5. The use of the pontoon must not cause any adverse effects on the amenity of the surrounding
areas including changes to light, views, air quality and noise.
6. Vessels berthed/moored at the pontoon must be located a minimum of 3.0 metres from the
prolongation of the property boundaries.
7. Vessels and boatlifting devices must be connected directly to the pontoon, and not located
side by side or in tandem with another vessel.
8. All structures must be designed and constructed such that they are free standing within the
waterway and are not connected to or behind the revetment wall.
9. All structures must have no detrimental effects on stormwater drains and/or easements.
10. Rigid handrails must be fitted on the gangway. The handrails must be of an open design and
in accordance with the approved plans.
11. No boatlifting devices are to be attached or moored at the pontoon structure for the purpose
of elevating a vessel above the water without Council approval.
12. There must be no electrical reticulation system carrying electricity in excess of 24 volts
beyond the revetment wall unless all switches and power outlets are positioned above the
1%AEP flood level.
13. Lighting associated with the use must be designed, installed, operated, and maintained in
accordance with Section 3 of AS4282 Control of the Obtrusive Effects of Outdoor Lighting.
14. The pontoon is to be used for private purposes only with no commercial operations to be
undertaken.
15. Boat repair activities are not permitted on site.
16. Wastewater and sullage must only be disposed of at approved pumpout facilities.
17. The mooring facility must not be utilised for live-aboard purposes.
18. Any construction and post construction activity is not to impact on the condition of the
waterway, and is to be conducted so as not to breach the Environmental Protection Act EPA
(1994) and the Environmental Protection (Water) Policy 2009.
19. Certification by a Registered Professional Engineer of Queensland that states that the
gangway, pontoon and mooring pile are constructed in accordance with best practice
methods and are structurally sound must be submitted to Council. This certification must be
submitted to Council within three (3) months of the completion of the works. A final inspection
and approval of the structure by Council’s Inspector is also required. Please contact Council’s
Development Assessment Branch on 5329 6500 to arrange the inspection.
Page 6 of 8
Document Set ID: 22751593
Version: 5, Version Date: 19/01/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning MCU23 0134.pdfRelated documentApplication case desk ↗
About this file
- File size
- 471 KB (small file)
- File type
No other editions are linked here.