Delegated Report - Code - Planning MCU23 0134 · MCU23/0134
20. This approval lapses where the construction of the jetty has not commenced within two (2)
years of the date of issue of the approval, unless application is made and approved by
Council for an extension.
21. After completion, the proposed works must be maintained in a sound state of repair in
accordance with the approved plans.
5. REFERRAL AGENCIES
The referral agencies applicable to this application are:
Referral Status Referral Agency and Referral Trigger Response
Address
Concurrence Department of State Schedule 10, Part 17, The agency provided its
Development, Division 1 – Tidal Works response on 13
Manufacturing, or November 2023
Infrastructure, and (Reference No. 2311-
work in a Coastal
Planning (SARA) 37725 SRA).
Management District
SARA – SEQ North A subsequent GIA
Region Office response was provided
(07) 5352 9701 or on 15 December 2023.
email: Copies of the
SEQNorthSARA@dilgp responses are attached
.qld.gov.au
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Aboriginal Cultural Heritage Act 2003
1. There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
carries out an activity must take all reasonable and practicable measures to ensure the
activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
duty of care. Substantial monetary penalties may apply to individuals or corporations
breaching this duty of care. Injunctions may also be issued by the Land and Resources
Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
General Advisory Notes
2. Council has undertaken an audit check of the Operational Works drawings in relations to the
proposed works. A detailed check of the calculations and drawings has not been undertaken,
as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects
of the engineering design. Council reserves the right to require further amendments and/or
additions at a later date should design errors become apparent.
3. The approval or conditions do not absolve the owner of the land from complying with all the
conditions of this approval and/or relevant Council By-Laws and Policies and/or relevant
statues and/or statutory regulations in the execution and/or performance of said works.
4. Council reserves the right to call up any performance bond held or levy charges against the
property, should emergency works be required to be undertaken by Council to make the site
safe due to inactivity on the development site for extended periods of time.
Page 7 of 8
Document Set ID: 22751593
Version: 5, Version Date: 19/01/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning MCU23 0134.pdfRelated documentApplication case desk ↗
About this file
- File size
- 471 KB (small file)
- File type
No other editions are linked here.