Other Change Decision Notice - Council Meeting Decision 131998 981211 5
Site Access and Driveways
99. A sealed access driveway must be provided from Kabi Road to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance
with an Operational Works approval, be generally in accordance with Elevation
Architecture’s Proposed Development Site Plan (A-DA-01.04, Rev. 17) dated 9
December 2024, and Council’s standard drawing RS-051 and any associated
addendum.
Car Parking
100. A minimum of 8 car parking spaces and 2 bus bays must be provided and marked on
the site and always made available and accessible while the use is open for business.
The works must be undertaken in accordance with an Operational Works approval, be
generally in accordance with Elevation Architecture’s Proposed Development Site Plan
(A-DA-01.04, Rev. 17) dated 9 December 2024 and must include in particular:
a. 8 staff parking spaces within the total, which are clearly marked for that purpose;
b. 1 disabled parking space/s within the total;
c. 2 bus bays;
d. a sealed turnaround facility sufficient sized to accommodate a 3-point turn
manoeuvre of a 14.5m rigid vehicle in accordance with section 5.5 of North Coast
Environmental Services’ Bushfire Hazard Assessment and Management Plan
(J001061, v.4) dated 11 September 2024;
e. marked pedestrian routes between the proposed car parking area(s) and the
clamping site area; and
f. dimensions, crossfalls and gradients in accordance with Australian Standard
AS2890: Parking Facilities.
101. Directional signage must be provided to direct visitors and patrons to the car parking
spaces provided on site.
Service Vehicles
102. Service vehicle parking, manoeuvring and standing spaces must be provided on the site.
The works include in particular:
a. regular access for vehicles up to a 14.5m rigid vehicle.
Stormwater Drainage
103. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with an Operational
Works approval, be generally in accordance with RECOR’s Stormwater Layout Plan
(C040, Rev. C) dated 26 September 2024 and must include in particular:
a. the disposal of stormwater without causing scour or damage to the subject site or
any adjoining properties; and
b. the extension of Council’s existing box culvert (600mm x 1200mm) to allow for the
Kabi Road upgrade. The extension must meet the requirements of QUDM and
Condition 97.
Easements
104. Unless otherwise agreed in writing by the relevant service provider, any public or third
party infrastructure located on the subject site must be placed within an easement
registered against the title of the property.
Page 15 of 21
Document Set ID: 23418211
Version: 10, Version Date: 02/01/2025