Other Change Decision Notice - Council Meeting Decision 131998 981211 5

of 21

Page text shows just the words. Original shows the document exactly as it was published.

                        b.      adequate manoeuvring about the intersection for a 12.5m and 14.5 rigid vehicle,
                                so that no part of the rigid vehicles exits the traffic lane(s); and
                        c.      widening of Kabi Road in accordance with Condition 97 ..
                        External Works – Kabi Road
                97.     Kabi Road must be upgraded for the full length of the road (i.e., between 59 Kabi Road
                        and Cootharaba Road). The works must be undertaken in accordance with an
                        Operational Works approval, be generally in accordance with Austroads’ A Guide to
                        Road Design Part 3, sections 5, 6 and 8 of BMC Traffic’s Traffic Engineering
                        Assessment Report (Doc ID: 22354477) dated 22 March 2023, The Noosa Plan 2020 –
                        PSP6 Engineering Design Standards, and include, but not be limited to:
                        a.      a design prepared by a suitably qualified person (RPEQ);
                        b.      a combined traffic lane width of 6.2m (2 x 3.1m);
                        c.      a shoulder width of 1.0m (with a minimum shoulder sealed width of 0.5m);
                        d.      a pavement design suitable to cater for heavy vehicles (i.e., rigid vehicles, buses,
                                etc.);
                        e.      all associated drainage infrastructure (i.e., table drain, culvert, etc.);
                        f.      the continuation of the existing stormwater box culvert to allow for the required
                                carriageway width;
                        g.      considerations to the existing residential driveway crossovers; and
                        h.      a sealed turnaround facility sufficiently sized to accommodate a 3-point turn
                                manoeuvre of a heavy rigid vehicle (HRV) located at the end of the road.
                        Fire Access Trail
                98.     The development site must be provided with an Emergency Bushfire Evacuation Route
                        connecting to Council’s “Road 176”. The emergency route is to be used for emergencies
                        only and is not to be used for deliveries or general access.
                        The works must be undertaken in accordance with an Operational Works approval and
                        Section 5.5 of North Coast Environmental Services’ Bushfire Hazard Assessment and
                        Management Plan (J001061, v.4) dated 11 September 2024, and include, but not be
                        limited to:
                        a.      a design prepared by a suitably qualified person (RPEQ) that is to an acceptable
                                standard to cater for a HRV, 14.5m rigid vehicle (i.e., bus) and appropriate fire-
                                fighting appliances;
                        b.      a design that allows for unbroken access for a HRV, 14.5m rigid vehicle (i.e., bus)
                                and appropriate fire-fighting appliances through the site (i.e., from “Road 176” to
                                all parking and manoeuvring areas and through to Kabi Road);
                        c.      a design that includes passing bays and turning areas;
                        d.      the emergency route, all internal roads and associated manoeuvring areas must
                                not exceed a gradient of 12.5%;
                        e.      the emergency route must have a maximum cleared width of 10.0 metres and a
                                minimum cleared width of 6.0 metres; and
                        f.      the necessary upgrades to “Road 176” and associated drainage
                                infrastructure, which must be maintained by the applicant during the life of the
                                development.
                        g.      Consultation must occur with the existing resident(s) that access “Road 176”
                                in relation to the proposed works.




                                                                                                             Page 14 of 21
Document Set ID: 23418211
Version: 10, Version Date: 02/01/2025
Log in to download the original file

Other Change Decision Notice - Council Meeting Decision 131998 981211 5.pdf · 214 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.