Other Change Decision Notice - Council Meeting Decision 131998 981211 5
a. The use or erection of a building or other structure associated with the use, has
not been commenced within four (4) years of the date of issue of the Development
Permit, unless application is made and approved by Council for an extension; or
b. the use of any premises pursuant to the Development Permit ceases.
55. Prior to the commencement of development, the developer must obtain the following
Development Permits:-
55.1 Development Permit for building works;
55.2 Development Permit for plumbing and drainage works;
55.3 Development Permit for operational works of landscaping, carparking and access;
55.4 Development Permit for reconfiguring a Lot (amalgamation)
The developer must obtain all of the other Development Permits referred to above, prior
to obtaining a Development Permit for building works, unless the Council agrees
otherwise.
Additional Conditions - 19 December 2024
When Conditions must be Complied With
56. Unless otherwise stated, conditions 56 to 108 relating to the Group Farm Stay
Accommodation and Associated Activities, of this Decision Notice must be complied with
prior to the use commencing, and then compliance maintained at all times while the use
continues.
Currency Period
57. The Group Farm Stay Accommodation and Associated Activities use lapses if the use
has not happened by 19 December 2026 unless an application to extend the currency
period is approved by Council.
Approved Plans
58. Development authorised by this approval must be undertaken generally in accordance
with the Approved Plans listed in the table below. The plans must be amended to
incorporate the amendments listed within the table below and resubmitted to Council
prior to the issue of any Development Permit for Operational Works
Plan No. Rev. Plan/Document Name Date
A-DA-01.02 09 Existing/Demo Site Plan prepared by 9/12/2024
Elevation Architecture
A-DA-01.04 17 Proposed Development Site Plan 9/12/2024
prepared by Elevation Architecture
A-DA-01.05 09 Permaculture Utilisation prepared by 9/12/2024
Elevation Architecture
A-DA-CL-01.03 D Site Plan – Clamping Village prepared by 8/11/2024
Elevation Architecture
A-DA-CL-03.02 E Floor Plan – Clamping 1 prepared by 8/11/2024
Elevation Architecture
A-DA-CL-03.03 D Floor Plan – Dining & Activity prepared 8/11/2024
by Elevation Architecture
Page 8 of 21
Document Set ID: 23418211
Version: 10, Version Date: 02/01/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original