Other Change Decision Notice - Council Meeting Decision 131998 981211 5

of 21

Page text shows just the words. Original shows the document exactly as it was published.

                Town Planning
                42.     Development undertaken in accordance with this approval must generally comply with
                        the approved plans of development.      The approved plans are numbered No.
                        G177.DCP.02 Figure 3 prepared by GNP Golf Design Pty Ltd and dated May 1998 and
                        as may be amended by these conditions.
                43.     The approval of the Sport and Recreation (golf course) component of the Integrated
                        Permaculture Designed Organic Orchard and Golf Course Complex, is only valid for as
                        long as the Agriculture use (Permaculture) is undertaken on this site. The Sport and
                        Recreation (Golf Course) use, and ancillary uses, lapses if the Permaculture use ceases
                        on the site.
                44.     The owner/operators of the proposed development are required to be members of the
                        Biological Farmers of Australia. Accordingly there is not be any use of non organic
                        chemicals on the site.
                45.     The Regional Manager, Cultural Heritage Program, Southeast Region, Environment
                        Protection Agency should be contacted immediately on (07) 3325 8425 should any
                        cultural artifacts be exposed during construction.
                46.     The proponent should give some consideration to rehabilitating the existing and
                        proposed waterway features, to a more natural state, by the use of native fauna and
                        flora. The Southern Fisheries Centre (Mr Bob Simpson, (07) 3817 9590 may be
                        contacted for advice on stocking native fish.
                47.     The clubhouse is limited to a size of 280m2. Any future application for the granting of
                        a Liquor Licence should be limited in the hours of the licence to not later than 10pm
                        Monday to Sunday, to minimise the potential impacts on surrounding residences. The
                        clubhouse is not permitted to operate after 10pm daily and is not to be utilised as a
                        Function Room.
                48.     The development must be undertaken and operated in a manner that causes no
                        detrimental effect upon the amenity of the neighbourhood by reason of excessive noise,
                        lighting nuisance or other emissions.
                49.     The open space and setback areas are to be landscaped in accordance with Council’s
                        Policy on Landscaping Guidelines and a properly prepared landscape plan. Such
                        landscaping is to be completed prior to the commencement of the golf course
                        component of the use and maintained at all times thereafter to the reasonable
                        satisfaction of the Director of Environment & Planning.
                50.     Existing trees on the site and within road reservice are to be retained, except where
                        required to be removed due to building operations or the conduct of the approved use.
                        The landscape plans referred to above are to denote areas of existing vegetation or
                        existing trees proposed to be retained.
                51.     Any advertising sign or device is to comply with the provisions of Council’s policies on
                        advertising.
                52.     The developer must submit security in the form of a cash bond or trading bank guarantee
                        to the sum of $20,000 to secure performance of all conidiations of this approval, prior to
                        the issue of a Development Permit for building works. The cash bond or trading bank
                        guarantee will be returned on performance of the conditions of approval less any costs
                        incurred by Council in respect of enforcing performance of this permit.
                53.     The requirements of this development approval are to be effected, prior to the use of the
                        premises. Council reserves the right to call upon the bond or guarantee sum referred
                        to in this approval to effect compliance with conditions.
                54.     This development Permit for material change of use of premises lapses if :-




                                                                                                        Page 7 of 21
Document Set ID: 23418211
Version: 10, Version Date: 02/01/2025
Log in to download the original file

Other Change Decision Notice - Council Meeting Decision 131998 981211 5.pdf · 214 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.