Skip to the record
The gold standard in government transparency.

Original source · versioned page text

Decision Notice - OPW22 0303 [As Published]

of 16

Page text shows just the words. Original shows the document exactly as it was published.

                      a.      Traffic Management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction.
                              ii.      Maintenance of safe vehicle and pedestrian access across the frontage of the
                                       site both during daily construction and after daily construction has ceased
                              iii.     Proposed fencing to the site during the construction phase of the development
                              iv.      Adequate parking arrangements for construction workers
                              v.       No queuing of trucks is permitted on residential streets, especially prior to
                                       7.00am. Further parked trucks must have engines turned off
                      b.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures
                      c.      Works programme identifying key components of the works and their respective
                              durations
                      d.      Establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic and services and other relevant issues
                      e.      Include a post out to the local residents and businesses advising of the proposed
                              development, the expected time frames and the site contact details
                      f.      Include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details.
                      g.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager
                              ii.      dispute resolution procedures
                      h.      For haulage operations involving significant volumes of excavated material being
                              transported onto or off the site: details on the location of external fill sites/sources, the
                              haulage route, type of vehicle to be utilised during filling operations and frequency of
                              usage. NB any damage to the existing road system as a result of haulage operations
                              shall be fully repaired at the applicant’s expense.
               12.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               13.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               14.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               15.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where required such confirmation must be
                      submitted for the respective hold points prior to any site inspection by Council Officers.
               16.    All works must be constructed and work procedure undertaken in accordance with:



                                                                                                            Page 4 of 16
Document Set ID: 22382210
Version: 3, Version Date: 21/04/2023
Log in to download the original file

Decision Notice - OPW22 0303 [As Published].pdf · 187 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.