Council archive · source document
Negotiated Report (Representations made) OPW22 0299 [As Published] · OPW22/0299
ED 22116 OPW-03 A Planting Plan prepared 9 November 2022
by Element Design
As amended by
conditions
ED 22116 OPW-04 A Planting Plan prepared 9 November 2022
by Element Design
As amended by
conditions
Applicant’s Representation
In summary the updated set of plans for approval incorporate a new gully pit in the kerb and
channel (instead of manhole) and changes to driveway profile to ensure overland flows along
western pathway discharge to street.
The changes do not affect the landscaping approved plans.
The change representations seek to update condition 1, approved plans
Assessment of Representation
The change to the design of the stormwater was assessed by both Operational Works and
Council’s design section and is considered acceptable.
It is recommended that the approved plans table be amended to read as follows:
Plan No. Rev. Plan/Document Name Date
21617-C001 D Locality Plan & Drawing 19 April 2023
Index prepared by TOD
Engineers and Project
Management
21617-C100 C Nominal Bulk Earthworks 23 February 2023
prepared by TOD
Engineers and Project
Management
21617-C200 D General Arrangement 19 April 2023
prepared by TOD
Engineers and Project
Management
21617-C201 C Site Sections prepared 23 February 2023
by TOD Engineers and
Project Management
21617-C202 D Roadworks Sections 19 April 2023
prepared by TOD
Engineers and Project
Management
Page 3 of 7
Document Set ID: 22424924
Version: 3, Version Date: 15/05/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Report (Representations made) OPW22 0299 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 94 KB (small file)
- File type
No other editions are linked here.