RFI response signed

of 2

Page text read automatically using OCR, there may be inaccuracies

Brian Naismith
B App Sc (Surv)
Consulting Cadastral Surveyor

11" August 2020
Ref 3365
Your Ref: RAL 19/0014

Chief Executive Officer
PO Box 141
TEWANTIN

QLD 4565

Att:

Billy Glover
Development Planner

RE: RESPONSE TO INFORMATION REQUEST
30 POTTERY STREET, POMONA
LOT 496 on Plan MCH491
Owner applicant Mrs Ellen Leape

Dear Sir

On behalf of the applicant, | hereby respond in full to Council’s Information Request
dated 13" March 2020.

Please find attached with this letter the following documents: -

* =19660-C1001_[A]-C1004_[A].pdf

= 19660 - Technical note on bio basin retaining walls. pdf

= 2020023_PotterySt_SMP_rev0.pdf

= Bushfire Hazard Assessment & Management Plan v1 - 30 Pottery St Pomona

2020.pdf

Item 1

The Civil Works General Arrangement plan prepared by Tod Consulting shows proposed
pedestrian pathway in Pottery Street. The crossing point to Red Street is proposed north side
of Red Street where it is considered safest. Typical Sections for Pottery Street and the New
Road also indicate the footpath design. It is noted pedestrian movement in Red Street is
provided for on grassed verges until its intersection with Reserve Street, near the local
supermarket. It is considered the pavement proposed reasonably enhances the existing
arrangements relevant to development of the subject land.

95 Groundwater Road, Southside Q 4570
M 0477 925 871 | E [email protected]

Log in to download the original (RFI response signed.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 1 page

Page 2

Brian Naismith
B App Sc (Surv)
Consulting Cadastral Surveyor

Items 2 & 3

The Stormwater Management Plan has been prepared by Aquaintel. Reviewing that document,
together with the Civil Drawings by Tod Consulting, it is considered all drainage and water
quality issues requested have been properly addressed. Retaining walls are incorporated in the
biobasin design, deemed reasonably justified in the technical note provided by Tod Consulting.

Items 4&5

The Civil Drawings by Tod Consulting indicate road design, both frontage road and new road.
Kerbing and widening have been incorporated as relevant to the proposed development, in
Pottery Street and its intersection with Red Street. Underground servicing is preliminary
designed, including stormwater drainage arrangements and sewerage (not requested in RFI).

Item 6

The Bushfire Hazard Assessment & Management Plan has been prepared by North
Coast Environmental Services. It addresses the required planning legislation and
finds the development proposed wholly compliant.

Should Council have any queries or require additional information please contact

me at your earliest convenience.

Regards

Zz

Brian Naismith
Consultant
0477 925 871

95 Groundwater Road, Southside Q 4570
M 0477 925 871 | E [email protected]

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.