Negotiated Decision Notice MCU20 0071 · MCU20/0071
a. A 2.0 metre wide concrete footpath within the road verge for the entire length of the
site’s frontage to Moorindil and Toolar Streets in accordance with Council’s Standard
Drawing RS-065 and with a varied width, if necessary, to address site constraints, but
at an absolute minimum width of 1.8 metres.
b. Must be extended, where necessary, beyond the frontages of the site to smoothly join
the existing pathway or to achieve compliant grades and standards.
c. A longitudinal section for the full length of the proposed pathway that demonstrates
compliant public pathway grades. The section should also indicate any required
earthworks (cut/fill) on the road verge.
d. Details for any required pram ramps in accordance with the applicable standards, and
Council’s requirements.
e. Any necessary handrail requirement for fall protection in compliance with the applicable
standards.
f. Any required adjustment to existing public services’ covers (eg water hydrant, Telstra
pit/s etc).
g. Any required stormwater drainage provisions (eg drainage measures to control surface
runoffs or stormwater ponding near sag points.
65. All necessary approvals from external service providers (eg Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
66. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting and prior to any works commencing.
67. A condition report including photographs of existing dividing fences, buildings and structures
on adjoining properties (including but not limited to retaining walls, fences, paved areas,
swimming pools, etc) that have a potential to be impacted on by the proposed development
works must be completed prior to any works commencing and submitted to Council and
agreed on at the prestart meeting.
68. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council at the prestart meeting.
69. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Landscape works;
c. Erosion and sediment control works;
d. Other relevant parties
70. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction
ii. Maintenance of safe pedestrian access across the frontage of the site both during
daily construction and after daily construction has ceased
iii. Proposed fencing to the site during the construction phase of the development
iv. Adequate parking arrangements for construction workers
Page 10 of 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Decision Notice MCU20 0071Related documentApplication case desk ↗
About this file
- File size
- 352 KB (small file)
- File type
No other editions are linked here.