Appendix C - Stormwater Management Plan

Attached to the e-mail MCU15/0095 & REC15/0022 Development Application Stormwater Mgmt Plan (2 of 3).

of 74

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Original PDF page 15, section 1. The text section number identifies this passage in the reader.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
TfA Project Group Pty Ltd                                                                         Stormwater Management Plan
                                                                                                       Development Application




   7.1.2      Performance objectives
   The objectives are:
          •   Minimise the amount of sediment entering Noosavilley’s waterways and stormwater drains;
          •   Minimise or prevent environmental harm to the City’s waterways and associated ecosystems;
          •   Minimise localised flooding caused by sediment runoff;
          •   Minimise exposure of soils.


   Table 17: Construction phase performance criteria

     Indicator                                                        Water Quality Objectives
     pH                                                               6.5 – 8.5
     Suspended Solids                                                 Annual Mean < 10mg/L
     Oils and Grease                                                  No visible films or odour
     Litter/ Gross pollutants                                         No anthropogenic (man-made) materials greater than
                                                                      5mm in any dimension
     Dissolved oxygen                                                 80-100% saturation


   7.1.3      Monitoring and Maintenance


   The general requirement of monitoring during the construction phase will be:
          •   Work activities are restricted to designated construction areas;
          •   Earthworks and site clearing are undertaken in accordance with an Erosion and Sediment Control Plan;
          •   Erosion and sediment control devices are to be constructed/installed in accordance with an Erosion and
              Sediment Control Plan;
          •   Inspection of sediment fences, erosion and sediment control structures/devices on a weekly basis as well
              as after any rain event exceeding 25mm in 24hrs (major storm event);
          •   Stormwater discharges from the site are not having any adverse effect on the downstream environment;
          •   Monitoring and recording of the performance of the drainage control devices including water quality
              testing where required;
          •   Any failure in the stormwater system shall be immediately rectified to prevent uncontrolled discharge
              from the site;
          •   Any failure to the stormwater system causing damage to surroundings should implement immediate
              remedial work to the damaged area.


   7.1.4      Responsibility and Reporting
          •   The contractor shall be responsible for monitoring the performance of all drainage control and erosion and
              sediment control devices;
          •   Records of any failures to devices should be kept and reported to the Construction Manager;
          •   Regular inspections of the devices shall be reported to the Construction Manager;
          •   Inspections of the devices after heavy rainfall shall be reported to the Construction Manager;




                            123 Eumundi Road (Cnr Walter Hay Drive), Noosaville QLD 4566                                    Page 9
Log in to download the original file

Appendix C - Stormwater Management Plan.pdf · 6.3 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.